On September 14, 2026, Governor Gavin Newsom signed AB 2168 by Assemblymember Buffy Wicks, titled “Active Transportation Program: guidelines.” The law changes what the California Transportation Commission (CTC) must include in the guidelines it uses to select projects for the Active Transportation Program (ATP), the state’s competitive grant program for walking, biking, and Safe Routes to School projects.
AB 2168’s changes to the Active Transportation Program apply on and after January 1, 2028, according to the chaptered bill summary. They broaden the transit access project types the guidelines must cover, including projects that expand access to transit in underserved or rural areas, require incentives for outside funding, require penalties for applicants that did not use earlier awards on time, and add a transit agency consultation step. The current cycle, the 2027 ATP, runs on the schedule in the CTC’s adopted 2027 ATP guidelines, with staff recommendations for the statewide and small urban and rural components set for November 2, 2026.
What happened
AB 2168 was first heard in the Assembly Committee on Transportation on April 20, 2026, and was chaptered by the Secretary of State on September 14 as Chapter 210, Statutes of 2026. It was one of several transportation measures on the Governor’s September 14 list, which also included AB 2788, the Assembly Transportation Committee’s transportation omnibus bill. Streetsblog California noted on September 15 that the Governor had until the end of the month to sign or veto legislation.
The ATP was created in 2013 by SB 99, which combined the state’s Safe Routes to School, bicycle, and recreational trails programs, according to the Assembly Transportation Committee analysis. The same analysis describes the program as funded by state and federal sources at approximately $123 million a year. Citing the CTC, it reports that the seventh cycle in 2025 received 277 project applications requesting $2.5 billion, about 15 times the $169 million available.
What AB 2168 changes in the ATP guidelines
According to the chaptered bill summary, on and after January 1, 2028, the ATP guidelines must:
- Cover transit access in eligibility. Eligible project types include safe routes to transit projects that encourage access to transit facilities and schoolbus stops by biking and walking, and projects that will expand access to transit in underserved or rural areas. The project selection criteria also add the potential for encouraging increased access to public transit.
- Include incentives for outside funds. The guidelines must include, rather than may include, incentives intended to attract funds other than program funds, in order to scale funding for larger or network-level active transportation improvements.
- Penalize unspent awards. The guidelines must include a progressive range of penalties, from a deduction of points to disqualification, for an applicant that failed to use previously received program funds in a timely manner. The Commission must consider factors outside the applicant’s control, which may result in no penalty or a delayed penalty.
- Require transit agency consultation. When a project is adjacent to an existing bus, shuttle, or paratransit route, the applicant must consult with the executive officer of a transit agency operating in the project corridor.
The bill changed during the session. As amended April 13, the Assembly committee analysis described penalties that would range from a deduction of points to disqualification, while considering factors not under an applicant’s control, and a new selection criterion on maximizing commitments of State Transportation Improvement Program (STIP) funds to ATP projects. That STIP criterion does not appear in the chaptered text. The Transportation Agency for Monterey County’s June bill matrix notes that May 18 amendments made the provisions active as of January 1, 2028. The California Bicycle Coalition, which sponsored the bill, described the final version on August 28 as expanding the program’s focus on walking and biking connections to public transportation and aligning ATP project corridors with STIP funding (the chaptered text does not reference STIP funding).
Key details and timeline
- September 14, 2026: AB 2168 signed and chaptered.
- November 2, 2026: CTC staff recommendations for the 2027 ATP statewide and small urban and rural components, per the program schedule. Applications for this cycle were due June 22, 2026.
- December 3-4, 2026: CTC adoption of the statewide and small urban and rural components.
- June 2027: MPO component recommendations (June 4) and adoption.
- January 1, 2028: AB 2168’s guideline requirements apply.
Caltrans states that ATP Cycle 8 is expected to include about $574M from federal, SB 1, and State Highway Account funding, programmed in fiscal years 2027-28 through 2030-31. The 2027 ATP Fund Estimate, adopted by the Commission in March 2026, states that the program is expected to provide approximately $619 million over the same four years, combined with existing resources. Under the CTC guidelines, funds are split 50 percent to the statewide component, 10 percent to small urban and rural areas, and 40 percent to the metropolitan planning organization (MPO) component, and each component must direct at least 25 percent of funds to projects benefiting disadvantaged communities. ATP projects do not require a match, though projects that leverage committed funding score higher.
The current guidelines already enforce delivery. Allocation must be requested in the fiscal year the funds are programmed, construction contracts must be awarded within six months of an approved allocation, and an agency has up to 36 months after award to complete the contract. If a deadline passes without an approved extension, the funds lapse and the project or phase is deleted from the program. No deadline will be extended more than once. AB 2168 adds a separate consequence: a record of unspent awards can count against an applicant in later competitions.
Who is affected
- Cities, counties, and regional agencies. The CTC guidelines list local, regional, or state agencies, including cities, counties, metropolitan planning organizations, and regional transportation planning agencies, among eligible applicants. The penalty provision applies to applicants that failed to use previously received program funds on time.
- Transit agencies. The consultation requirement brings transit executive officers into projects along existing bus, shuttle, and paratransit routes.
- Rural and small urban regions. In April, the Nevada County Transportation Commission, listed as opposed unless amended, wrote that the penalty approach was overly punitive and does not adequately account for delays outside a lead agency’s control, such as permitting, utility coordination, and right-of-way.
- Other agencies. The Riverside County Transportation Commission was also listed in opposition, and the Monterey-Salinas Transit District in support if amended.
- Agencies with committed STIP programs. The Transportation Agency for Monterey County, which listed a “support if amended” position in June, noted that the April 13 version’s STIP criterion could disadvantage Monterey applications because 100% of TAMC’s 2026 STIP capacity was programmed to priority rail and highway projects. That criterion does not appear in the chaptered text.
Once the provisions apply, an applicant’s record of using earlier ATP awards on time becomes part of how its new applications are judged. Agencies sorting out how an ATP application fits with STIP, local, and other grant funds can see how DBMAC approaches program matching and readiness on its public funding and infrastructure page.
What to watch
- November 2 staff recommendations. The 2027 ATP schedule sets the statewide and small urban and rural recommendations for November 2, ahead of the December 3-4 adoption.
- Guideline development for later cycles. Existing law requires the CTC to develop ATP guidelines and selection criteria in consultation with an ATP Workgroup. The penalty range, the incentive structure, and the transit consultation step are guideline requirements, so their details are set through that process.
- Delivery records on existing awards. Agencies can compare current ATP projects against the allocation, contract award, and completion deadlines in Section 31 of the guidelines and the extension conditions in Section 32.
- Other funding windows. DBMAC tracks open state and federal grant programs on its weekly Funding Opportunities page.