CAISO Large Load Interconnection: What the October 28 Board Approval Means for Data Center Sites

The California ISO will take its large load proposal to FERC by November 16. Here is what the Board approved, how flexible interim service would work, and why the utility tariff filings matter just as much.

Daron McDaniel

By Principal, DBMAC Strategies

Published 7 min read

CAISO large load interconnection rules moved a step closer to federal review on October 28, 2026, when the California ISO Board of Governors approved a proposal for connecting data centers, manufacturing operations, and other large loads to the grid. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline.

For a developer, landowner, or local agency looking at a site that could draw 50 megawatts or more, the proposal bears on who processes a request, how long studies take, whether a project can connect before upgrades finish, and who carries the cost. The details below come from the ISO’s September 24 draft final proposal and its draft tariff language posted October 30. The text filed at FERC is the version to rely on once it is available.

What the CAISO Board approved

The proposal responds to a June 18, 2026 FERC order. FERC found that CAISO’s tariff and the tariffs of its Participating Transmission Owners (transmission owners such as PG&E, SCE, and SDG&E) appear to be unjust, unreasonable, or unduly discriminatory, and directed them to either defend those tariffs or explain what changes would fix them. FERC issued six tailored orders to the six regional grid operators under its jurisdiction.

The central element, according to the ISO’s release, is a flexible interim load interconnection, which would let a large load connect before its network upgrades are finished, with enforceable limits tied to grid conditions. The release also describes a framework to prevent cost shifting, requirements for co-located load and generation, and a new monthly window to review transmission additions. Chief Executive Elliot Mainzer said the response “will improve planning and operational awareness” of new large loads.

The proposal also cites a California Energy Commission forecast that data center load on the CAISO-managed grid will increase by 1.8 gigawatts by 2030 and 4.7 gigawatts by 2035.

Key details and timeline

What counts as a large load

The draft tariff defines a large load as an end user at a single site, behind one or more points of interconnection to the CAISO Controlled Grid, with a peak load of 50 MW or greater. The ISO declined PG&E’s suggested 20 MW threshold, and says the definition may shift to avoid conflict with reliability standards under development at the North American Electric Reliability Corporation (NERC). Distribution-connected loads fall outside the definition, although the ISO says any network upgrades they trigger can be considered in its transmission planning process.

Where requests and studies go

The ISO is not taking over load interconnection. Requests continue to go to the transmission owner under its own tariff, and the transmission owners keep the bulk of the study work. As a minimum standard, the ISO expects them to complete studies within 60 to 90 days. The draft has the ISO reviewing out-of-cycle transmission additions monthly to fit that window. Projects whose upgrades arrive after the planned connection date would not receive firm service until those upgrades are in service, and the ISO identifies them as candidates for interim service. For the retail side of this path in PG&E territory, see our guide to California data center power interconnection.

How flexible interim service works

The draft tariff describes this as curtailable, interim service. Before energization, the ISO, the transmission owner, and the large load or its agent would sign an agreement covering when curtailment happens, the mechanism, who performs it, notice and response times, interim operating limits, and the upgrades that end the arrangement. The ISO would post these agreements on its website.

The ISO declined to set a time or capacity cap on the service, and says each arrangement would likely be tailored to the load’s point of interconnection and constraints. When upgrades finish, the load would move to firm service. The ISO also states that the service is not intended to address supply constraints. A permanent flexible option was deferred to a future initiative.

Operating requirements

The draft final proposal calls for hourly forecasts covering the operating day and a rolling 7-day period, with day-ahead forecasts due by 7:00 a.m. Pacific the prior day, submitted through the scheduling coordinator of the load’s load-serving entity, plus telemetry and outage data. The October 30 draft tariff adds frequency and voltage ride-through tables, recovery to at least 90 percent of pre-disturbance power within three seconds after voltage recovers, and a ramp limit of 20 megawatts per minute measured over a rolling 10-minute interval. It also requires the transmission owner to be able to disconnect or isolate a large load to maintain reliability.

Cost responsibility

The ISO does not propose a “top-down” cost allocation in its own tariff. It says cost allocation rules belong in transmission owner tariffs, and that the transmission owners are leading development of a pro forma cost recovery agreement. The ISO also proposes that transmission owners account for large load contributions when setting their transmission revenue requirements. The owner-specific terms will come from their filings.

Co-located generation

The proposal would require co-located large loads to be sub-metered separately from onsite generation and to pay for regulation and black start services on a gross load basis. Large loads with backup generation used only during outages or islanding, and those with non-exporting behind-the-meter generation, would not need a CAISO resource interconnection request, though they would need control technologies. Other co-located configurations with exporting generation would need parallel review by the ISO and the transmission owner.

Timeline

Who is affected

A site team weighing a project of this size can test these points alongside water, labor, and entitlement history in an economic development site assessment.

What to watch

Frequently asked questions

What is a large load under the CAISO proposal?

The draft tariff language defines it as an end user at a single site, behind one or more points of interconnection to the CAISO Controlled Grid, with a peak load of 50 MW or greater. Distribution-connected loads fall outside that definition.

What is flexible interim load interconnection?

It is a proposed curtailable, interim service that lets a large load connect before its network upgrades or interconnection facilities are complete. The ISO's proposal says the load would switch to firm service once upgrades are complete, and it sets no time or capacity cap.

Who processes a large load interconnection request in the CAISO footprint?

The transmission owner does, under its own tariff. The ISO's proposal keeps that structure: transmission owners handle most applications and studies, while the ISO reviews study results and aligns them with transmission planning. The ISO expects studies to be completed within 60 to 90 days.

When would the CAISO large load rules take effect?

No date is final. The ISO will file by November 16, and FERC will decide whether the proposal satisfies its order. The October 30 draft tariff shows a bracketed February 14, 2027 or effective date for separating existing requests from new ones.

Who pays for network upgrades for a large load?

The ISO says those rules belong in transmission owner tariffs and does not propose a top-down allocation of its own. The transmission owners are leading a pro forma cost recovery agreement, so owner-specific terms will come from their filings.

Sources

  1. CAISO Board advances new procedures for connecting large loads quickly and reliably (opens in a new tab)California Independent System Operator, October 28, 2026
  2. Large Load Enhancements: Draft Final Proposal (opens in a new tab)California Independent System Operator, September 24, 2026
  3. Second Revised Draft Tariff Language: Large Loads Order to Show Cause (opens in a new tab)California Independent System Operator, October 30, 2026
  4. Order Instituting Section 206 Proceeding (195 FERC ¶ 61,214), Docket No. EL26-71-000 (opens in a new tab)Federal Energy Regulatory Commission, posted by CAISO, June 18, 2026
  5. Motion for Abeyance, Large Loads and Co-located Loads, Docket No. EL26-71 (opens in a new tab)California Independent System Operator, August 3, 2026
  6. FERC Order to Show Cause for Large Loads: Draft Tariff Language Stakeholder Meeting (opens in a new tab)California Independent System Operator, October 19, 2026
  7. Large Loads Initiative: Draft final proposal and draft tariff language posting, meetings on 10/1/26 and 10/19/26 (opens in a new tab)California Independent System Operator, September 24, 2026
  8. Large Loads stakeholder initiative page (opens in a new tab)California Independent System Operator, Most recent posting October 30, 2026

Energy and data centers

Weighing a 50 MW site? Confirm the power path first.

The ISO proposal and the utility tariff filings that accompany it shape how quickly a large load can connect, on what terms, and at whose cost. DBMAC Strategies helps developers, landowners, and local agencies assess power, water, and site readiness and map the approvals a project will need. How DBMAC works on energy and data center projects.

Any matter before a public body on which Daron holds or has held a seat, whether county, regional, or statewide, is reviewed for conflicts before any substantive conversation. See all of his seats.