CAISO large load interconnection rules moved a step closer to federal review on October 28, 2026, when the California ISO Board of Governors approved a proposal for connecting data centers, manufacturing operations, and other large loads to the grid. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline.
For a developer, landowner, or local agency looking at a site that could draw 50 megawatts or more, the proposal bears on who processes a request, how long studies take, whether a project can connect before upgrades finish, and who carries the cost. The details below come from the ISO’s September 24 draft final proposal and its draft tariff language posted October 30. The text filed at FERC is the version to rely on once it is available.
What the CAISO Board approved
The proposal responds to a June 18, 2026 FERC order. FERC found that CAISO’s tariff and the tariffs of its Participating Transmission Owners (transmission owners such as PG&E, SCE, and SDG&E) appear to be unjust, unreasonable, or unduly discriminatory, and directed them to either defend those tariffs or explain what changes would fix them. FERC issued six tailored orders to the six regional grid operators under its jurisdiction.
The central element, according to the ISO’s release, is a flexible interim load interconnection, which would let a large load connect before its network upgrades are finished, with enforceable limits tied to grid conditions. The release also describes a framework to prevent cost shifting, requirements for co-located load and generation, and a new monthly window to review transmission additions. Chief Executive Elliot Mainzer said the response “will improve planning and operational awareness” of new large loads.
The proposal also cites a California Energy Commission forecast that data center load on the CAISO-managed grid will increase by 1.8 gigawatts by 2030 and 4.7 gigawatts by 2035.
Key details and timeline
What counts as a large load
The draft tariff defines a large load as an end user at a single site, behind one or more points of interconnection to the CAISO Controlled Grid, with a peak load of 50 MW or greater. The ISO declined PG&E’s suggested 20 MW threshold, and says the definition may shift to avoid conflict with reliability standards under development at the North American Electric Reliability Corporation (NERC). Distribution-connected loads fall outside the definition, although the ISO says any network upgrades they trigger can be considered in its transmission planning process.
Where requests and studies go
The ISO is not taking over load interconnection. Requests continue to go to the transmission owner under its own tariff, and the transmission owners keep the bulk of the study work. As a minimum standard, the ISO expects them to complete studies within 60 to 90 days. The draft has the ISO reviewing out-of-cycle transmission additions monthly to fit that window. Projects whose upgrades arrive after the planned connection date would not receive firm service until those upgrades are in service, and the ISO identifies them as candidates for interim service. For the retail side of this path in PG&E territory, see our guide to California data center power interconnection.
How flexible interim service works
The draft tariff describes this as curtailable, interim service. Before energization, the ISO, the transmission owner, and the large load or its agent would sign an agreement covering when curtailment happens, the mechanism, who performs it, notice and response times, interim operating limits, and the upgrades that end the arrangement. The ISO would post these agreements on its website.
The ISO declined to set a time or capacity cap on the service, and says each arrangement would likely be tailored to the load’s point of interconnection and constraints. When upgrades finish, the load would move to firm service. The ISO also states that the service is not intended to address supply constraints. A permanent flexible option was deferred to a future initiative.
Operating requirements
The draft final proposal calls for hourly forecasts covering the operating day and a rolling 7-day period, with day-ahead forecasts due by 7:00 a.m. Pacific the prior day, submitted through the scheduling coordinator of the load’s load-serving entity, plus telemetry and outage data. The October 30 draft tariff adds frequency and voltage ride-through tables, recovery to at least 90 percent of pre-disturbance power within three seconds after voltage recovers, and a ramp limit of 20 megawatts per minute measured over a rolling 10-minute interval. It also requires the transmission owner to be able to disconnect or isolate a large load to maintain reliability.
Cost responsibility
The ISO does not propose a “top-down” cost allocation in its own tariff. It says cost allocation rules belong in transmission owner tariffs, and that the transmission owners are leading development of a pro forma cost recovery agreement. The ISO also proposes that transmission owners account for large load contributions when setting their transmission revenue requirements. The owner-specific terms will come from their filings.
Co-located generation
The proposal would require co-located large loads to be sub-metered separately from onsite generation and to pay for regulation and black start services on a gross load basis. Large loads with backup generation used only during outages or islanding, and those with non-exporting behind-the-meter generation, would not need a CAISO resource interconnection request, though they would need control technologies. Other co-located configurations with exporting generation would need parallel review by the ISO and the transmission owner.
Timeline
- June 18, 2026: FERC issues its order in Docket No. EL26-71.
- August 3: CAISO asks FERC to hold the case in abeyance until November 16; FERC’s order accepting the request is dated August 14.
- September 24: Draft final proposal posted; comments were due October 15.
- October 28: Board approval. Second revised draft tariff language follows on October 30.
- November 16: Section 205 tariff filings from the ISO and the transmission owners.
- Within 30 days of those filings: Interested entities may respond, under the terms of the order.
Who is affected
- Data center and manufacturing developers: projects at 50 MW or more with a point of interconnection on the CAISO-controlled grid. Peak size and connection point together decide whether the definition applies.
- Landowners and site sellers: under the proposal, the transmission owner, the connection point, and the schedule for any required upgrades would bear on whether a parcel could receive firm or interim service.
- Generation and storage owners: existing generators adding large loads would interconnect under transmission owner tariffs, and the ISO encourages them to seek updates to their interconnection agreements if needed.
- Cities, counties, and special districts: the ISO proposal addresses transmission service and grid operations, not local land use entitlements. Agencies reviewing a project can ask which service type and study status the applicant holds.
A site team weighing a project of this size can test these points alongside water, labor, and entitlement history in an economic development site assessment.
What to watch
- The transmission owner filings. Applications, study procedures, deposits, cost recovery, and interim service agreements sit largely in these tariffs. Most stakeholders asked to see those proposals before filing, according to the ISO.
- The transition date. The draft tariff excludes loads that are operational or have a complete request with the transmission owner before a bracketed date, shown as “February 14, 2027/effective date,” unless the load later modifies or increases. The filed text will settle that date.
- The CEC demand forecast. The ISO says the most effective way to reflect new large loads in its transmission planning is through the CEC forecast, finalized in the December timeframe each year.
- Working groups and future initiatives. After filing, the ISO plans working group meetings on implementation details. It has also said it will take up electrically proximate load and generation in a future initiative, and that any necessary software changes would begin in 2027, with completion targeted by 2030.
- FERC’s decision. FERC will determine whether the proposal satisfies its order. The ISO says the policies apply to new large loads only, after the tariff revisions are approved and effective.