California Data Center Laws: What the Seven Bills Signed September 21 Require

Governor Newsom signed seven data center bills on September 21. Here is what they require on electricity costs, water, reporting, and CEQA review, and the 2027 and 2028 dates projects need to plan around.

Daron McDaniel

By Principal, DBMAC Strategies

Published Last updated 9 min read

California data center laws changed on September 21, 2026, when Governor Gavin Newsom signed seven bills covering electricity costs, water use, energy reporting, and environmental review for data center projects. The Governor’s office said the laws give communities more information about energy, water, workforce, and land use. For developers, landowners, and the cities and counties that permit these facilities, the package changes what a project must disclose, what it pays for, and how it moves through local approval.

Several of the most significant provisions carry 2027 and 2028 dates, and much of the detail will be set by the California Public Utilities Commission (CPUC). This article covers what each law does, the dates that matter, and who needs to plan around them.

What happened

The Governor’s September 21 signing announcement lists the seven bills. Each chapter number below links to the chaptered text on the Legislature’s website:

Senator Steve Padilla’s office reported that SB 886 passed the Senate 28 to 10 and the Assembly 62 to 7, and SB 887 passed 30 to 8 and 59 to 11. The Legislature’s vote record shows that SB 1168 passed the Assembly 78 to 0 on August 28, and the Senate concurred 39 to 0 on August 30.

Electricity: new tariffs and who pays

Three bills address electricity costs. According to Senator Padilla’s office, SB 886 and AB 2383 require data centers to pay transmission upgrade costs, cover generation costs, and bear a larger share of wildfire mitigation and liability costs than they do today.

SB 886: interconnection and early exit

As chaptered (Chapter 438, Statutes of 2026), SB 886 requires the CPUC to establish new tariffs or update existing electric rules for data centers by January 1, 2028 (Public Utilities Code Section 945.2). The transmission-level interconnection tariff must assign cost responsibility for all transmission facility upgrades and usage to the data center, and must include an early termination fee for a data center that departs the electrical system within 10 years of its initial interconnection or fails to achieve adequate load ramp up, as determined by the CPUC (Section 945.3). That tariff applies to data centers entering new interconnection agreements for transmission-level retail service on or after January 1, 2027. Before the CPUC approves the tariff, a utility may submit an exceptional case filing for a contract with a data center seeking transmission-level service after January 1, 2027 (Section 945.9). A September 25 summary by Ballard Spahr, published by the National Law Review, summarizes the law for industry readers. That summary gives January 1, 2027 as the date for community choice aggregators and electric service providers to adopt generation tariffs; the chaptered bill sets January 1, 2028. A Pillsbury summary from September 1 adds that interconnection applicants would have to disclose applications for the same data center in other utility territories.

AB 2383: generation costs

As chaptered (Chapter 435, Statutes of 2026), AB 2383 requires the CPUC, in a new or existing proceeding, to require each investor-owned electrical corporation to file a transmission and distribution service tariff and a generation service tariff for data centers. The CPUC may not set the generation tariff’s demand threshold above 25 megawatts. Each community choice aggregator and electric service provider must adopt its own data center generation tariff by January 1, 2028. The generation tariffs must make data centers pay for incremental generation cost increases for a minimum of 10 years. Pillsbury notes that qualifying zero-emission behind-the-meter resources can reduce a data center’s obligation to pay.

SB 1168: a rate structure assessment

SB 1168 takes a different approach. Senator McNerney’s office describes it as requiring the CPUC to assess methods to ensure data centers pay their fair share for transmission and distribution upgrades and for their share of load increases, and to alleviate rate pressures on residential customers.

Water and reporting: what applicants disclose

The Governor’s office summarized the water provisions as requiring proposed data centers to provide information to local governments and water suppliers, and stated that any upgrades needed to supply water would be paid for by the data center.

AB 2469 ties water disclosure to local approval. As chaptered (Government Code Section 65964.7, Chapter 436), it prohibits a city or county from approving a permit for a new data center, or an expansion that increases maximum peak water use, unless conditions are met. Those include a water supply assessment, projected water use and water efficiency measures, workforce disclosures, and, beginning January 1, 2028, a water scarcity plan with measures for different drought scenarios. The applicant must also assume the full cost of any water conveyance, treatment, storage, or distribution improvements needed to serve the project, as determined by the water supplier.

AB 2619 works through business licenses. The Assembly Water, Parks, and Wildlife Committee’s April analysis of an earlier version of the bill describes three tiers, with a Type I or hyperscale facility defined as one with more than 10,000 servers or a power consumption of more than 25 megawatts. Before an initial business license, an operator gives its water supplier, under penalty of perjury, a good faith estimate of expected water use, the anticipated source of water, and projected water use volumes for the maximum day, maximum month, and average year, and reports the same estimates on the license application. At each renewal it reports its annual water use for the preceding calendar year, under penalty of perjury, on the business license renewal application to the city or county. Urban water suppliers consider data center demand in water shortage planning.

AB 1577 covers energy reporting. The Assembly Utilities and Energy Committee’s April analysis describes it as requiring data centers to report energy usage and efficiency information to the California Energy Commission (CEC), which publishes the data in anonymized, aggregated form. Data centers also submit specified information to local agencies when seeking authorization to build or operate.

Environmental review: SB 887 and CEQA

The Governor’s office described the land use provisions as making data centers ineligible for blanket environmental exemptions and requiring them to meet state energy, water, and fuel standards before any judicial streamlining could be approved. The Assembly Utilities and Energy Committee’s June analysis summarized SB 887 as one that prohibits data centers from receiving a categorical exemption from the California Environmental Quality Act while setting criteria for streamlining. As chaptered (Chapter 439, Statutes of 2026), new Public Resources Code Section 21084(f) bars a categorical exemption for a project carried out or approved in furtherance of a data center. For that rule, a data center does not include a publicly funded research facility, a public safety facility, a publicly funded national security facility, a publicly owned facility, other utility facilities such as a telecommunications provider’s assets, or a research facility of an independent college or university.

That streamlining runs through certification as an environmental leadership development project. As chaptered (Chapter 439), the lead agency must certify that a data center project meets criteria that include:

  • Paying in advance the full cost of interconnection and not increasing fossil fuel consumption within the state.
  • Zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand.
  • Using onsite zero-carbon energy storage to provide demand response services to the electrical grid.
  • Relying on zero-carbon generation located behind the meter to the maximum extent feasible.
  • An enforceable commitment, with the entity serving its load or a local publicly owned utility, to fully pay all electrical grid investments needed to serve the data center, including new generating capacity, with a process for an early termination fee.
  • Recycled water and water-efficient technology or waterless cooling.
  • 100 percent zero-carbon electricity for hourly needs within five years of initial operations, 75 percent newly developed.
  • One or more legally binding community benefits agreements with community-based organizations.
  • Meeting the requirements of Public Resources Code Sections 25545.3, 25545.3.3, and 25545.3.5.

Key dates and timeline

  • August 31, 2026: SB 886 and AB 2383 passed both houses, per Pillsbury.
  • September 21, 2026: All seven bills signed.
  • January 1, 2027: SB 886’s transmission interconnection tariff applies to data centers entering new interconnection agreements for transmission-level retail service on or after this date (Section 945.3(d)).
  • January 1, 2028: Deadline for the CPUC to establish new tariffs or update rules under SB 886, and for each community choice aggregator and electric service provider to adopt a data center generation tariff under AB 2383; AB 2469 water scarcity plans begin to apply.

Who is affected

  • Data center developers and site selectors. Interconnection cost responsibility, multi-year generation payments, and early termination fees change the cost picture for new transmission-level projects, and the permit-stage disclosures add to the application package.
  • Landowners marketing sites for large loads. Water supply assessments and power costs at the permit stage make power and water readiness part of how a site is evaluated.
  • Cities and counties. Local approvals depend on the AB 2469 disclosures, and SB 887 removes categorical CEQA exemptions for these projects.
  • Water suppliers, which receive AB 2619 estimates and account for data center demand in shortage planning.
  • Utilities, community choice aggregators, and electric service providers, which must file or adopt the new tariffs.

For a landowner or community weighing a large-load project, an early review of power, water, and site readiness now carries more weight in deciding whether a site can move forward.

The state laws are not the only change for large sites: see CAISO large load interconnection for the ISO’s proposal covering loads of 50 MW or more.

What to watch

Much of the detail will be set through CPUC proceedings rather than in the statutes. Pillsbury advised utilities to anticipate CPUC filings addressing threshold design, service categories, cost causation, and noted that the legislation permits interim utility agreements before final statewide rules. Other items to track are the CEC’s reporting process under AB 1577 and how cities and counties fold the AB 2469 and AB 2619 requirements into their permit and business license procedures.

Projects already in the pipeline should confirm which provisions apply to them, starting with whether an interconnection agreement will be signed before or after January 1, 2027, and whether local approvals will come before the water scarcity plan requirement begins in 2028.

Frequently asked questions

Who pays for grid upgrades to serve a new California data center?

Under SB 886 as chaptered (Chapter 438, Statutes of 2026), the CPUC's transmission interconnection tariff assigns cost responsibility for transmission upgrades and usage to the data center, and requires an early termination fee if the data center departs the system within 10 years of interconnection or fails to achieve adequate load ramp up. AB 2383 requires them to pay incremental generation cost increases for at least 10 years.

Can a California data center still use a CEQA categorical exemption?

Generally no. SB 887 (Chapter 439, Statutes of 2026) prohibits a categorical exemption for projects in furtherance of a data center, with exceptions for publicly funded research, public safety, national security, publicly owned, and utility facilities and for research facilities of independent colleges and universities. A project that meets criteria on interconnection and grid costs, zero-carbon power and storage, water use, and community benefits agreements can seek certification as an environmental leadership development project.

What water information must a data center provide before local approval?

AB 2469 conditions city and county approval on a water supply assessment, projected water use and efficiency measures, and workforce disclosures, plus a water scarcity plan beginning January 1, 2028. The applicant must also pay the full cost of any water infrastructure improvements needed to serve the project. AB 2619 adds water use estimates to the business license process.

What does AB 1577 require data centers to report?

AB 1577 requires data centers to report energy usage and efficiency information to the California Energy Commission, which publishes the data in anonymized, aggregated form. Data centers also submit specified information to local agencies when seeking approval to build or operate.

Sources

  1. SB 886 (Padilla), Chapter 438, Statutes of 2026: California Technology Innovation and Ratepayer Protection Act (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  2. SB 887 (Padilla), Chapter 439, Statutes of 2026: CEQA: environmental leadership development projects: data centers: geothermal powerplant projects (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  3. AB 2469 (Papan), Chapter 436, Statutes of 2026: Data centers: water use disclosures (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  4. AB 2383 (Zbur), Chapter 435, Statutes of 2026: Electricity: data centers (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  5. SB 1168 (McNerney) bill votes (opens in a new tab)California Legislative Information, Assembly August 28, 2026; Senate concurrence August 30, 2026
  6. Governor Newsom signs most comprehensive data center laws in the nation, providing communities more control on water, electricity, and land use (opens in a new tab)Office of Governor Gavin Newsom, Sep 21, 2026
  7. Nation-Leading Data Center Regulations Signed Into Law (opens in a new tab)Office of Senator Steve Padilla, California State Senate, September 21, 2026
  8. Legislature Greenlights McNerney's Bill to Ensure Data Centers Pay Their Fair Share (opens in a new tab)Office of Senator Jerry McNerney, California State Senate, August 30, 2026
  9. AB 2383 (Zbur) Analysis: Electricity: large energy use facilities (opens in a new tab)Senate Committee on Energy, Utilities and Communications, Hearing Date: 6/30/2026
  10. SB 887 (Padilla) Analysis (opens in a new tab)Assembly Committee on Utilities and Energy, Date of Hearing: June 24, 2026
  11. AB 2469 (Papan) Analysis (opens in a new tab)Assembly Committee on Local Government, Date of Hearing: April 22, 2026
  12. AB 2619 (Papan) Analysis: Water resources: data centers (opens in a new tab)Assembly Committee on Water, Parks, and Wildlife, Date of Hearing: April 14, 2026
  13. AB 1577 (Bauer-Kahan) Analysis: Data centers: reporting (opens in a new tab)Assembly Committee on Utilities and Energy, Date of Hearing: April 8, 2026
  14. California Signs Sweeping Data Center Energy Laws (opens in a new tab)Ballard Spahr LLP, published by The National Law Review, September 25, 2026
  15. California Data Center Deal Puts New Large Loads on a Cost-Causation Track (opens in a new tab)Pillsbury Winthrop Shaw Pittman LLP, 09.01.26
  16. AB 2619 (Papan), Chapter 437, Statutes of 2026: bill page and chaptered digest (opens in a new tab)CalMatters Digital Democracy, Chaptered September 21, 2026
  17. AB 2383 (Zbur), Chapter 435, Statutes of 2026: bill page and chaptered digest (opens in a new tab)CalMatters Digital Democracy, Chaptered September 21, 2026

Energy and data centers

Weighing a data center site? Plan for the new rules early.

California's new data center laws add tariff, water, reporting, and CEQA steps to new projects, with key dates in 2027 and 2028. DBMAC Strategies helps developers, landowners, and local agencies assess power, water, and site readiness and map the approvals a project will need. How DBMAC works on energy and data center projects.