California Data Center Power Interconnection: Utility Rules, Timelines, and Local Approvals

PG&E's interim Rule 30 sets who pays to connect a data center at transmission voltage, and key parts of it are still being decided. Here is how the utility rules, the state forecast, and the other approvals fit together.

Daron McDaniel

By Principal, DBMAC Strategies

Published Last updated 9 min read

California data center power interconnection now runs through a set of utility rules that are still being written. For sites in Pacific Gas and Electric Company territory, the governing document is Electric Rule 30, a tariff for retail customers served at transmission voltage, which the California Public Utilities Commission allowed PG&E to use on an interim basis in Decision 25-07-039 while the full application remains open. The interim rule decides who pays for which facilities, what a customer must submit, and what is still undecided.

The utility is only one part of the approval path. This guide covers the utility rules, the timelines the record shows, and the other approvals a project needs. It was first published in mid-July 2026 and updated in October 2026.

Why large loads needed a new rule

Before Rule 30, PG&E had no retail tariff for customers connecting at transmission voltage. Its existing tariffs covered wholesale transmission connections under federal rules and distribution-level service under Electric Rules 15 and 16, but not retail customer energization at transmission levels. Each project was handled as an exceptional case, filed as a Tier 3 advice letter for individual Commission review.

Demand for that kind of service has grown. According to the Public Advocates Office’s opening brief, PG&E stated that it interconnected 24 transmission-level customers between 2014 and 2022, and that in the last two years it received 40 applications, with 75 percent of the requests coming from data centers. In a January 28, 2026 presentation to an Assembly informational hearing, PG&E said Rule 30 would eliminate more than 12 months, covering negotiation plus 9 to 12 months for a Tier 3 advice letter and CPUC approval.

How interim Rule 30 works

The interim tariff applies to non-residential applicants served at transmission voltages from 50 kV up to and including 230 kV, with PG&E deciding the service voltage. Under the application, customers interconnecting above 230 kV would use exceptional case filings.

The four facility types

The decision sorts interconnection work into four types: dedicated transmission service facilities (Type 1), substation or switching station interconnection upgrades (Type 2), interconnection network upgrades that adapt the network to serve the customer (Type 3), and transmission network upgrades to the existing grid (Type 4). Under the interim rule, customers provide the full initial costs of Facility Types 1-3 through advances or actual cost payments, and Type 4 work is eligible when the customer provides 100 percent of the project cost as a pre-funded loan.

PG&E’s first compliance tariff was rejected by the Energy Division Director on November 19, 2025. The replacement, Advice Letter 7772-E, filed December 4, 2025, states that the applicant shall provide a pre-funding loan for 100 percent of the actual costs of all Type 4 upgrades its request causes, with repayment left to the Commission’s final decision.

What is deferred

The interim decision deferred refunds of advances and actual cost payments to the final decision, and states that no interest will accrue on funds advanced while the interim rule is in effect. Contracts signed under the interim rule stay in place if Rule 30 later changes, but remain subject to the final decision on refunds, interest, and loan repayment.

What an applicant provides

The tariff requires an applicant to include a forecast of expected load for the first ten (10) years of service, and to provide land rights on its own premises at no cost to PG&E. The form agreement ties the estimated in-service date to PG&E’s Preliminary Engineering Study report and lists the conditions that can move it, including scope changes and late payment of invoices. Where the site is inside a community choice aggregator’s territory, PG&E must send the CCA a copy of the application within 20 business days of receiving it.

Key details and timeline

Under that settlement, PG&E would provide quarterly reports on transmission-level customers that have applied but are not yet energized, and annual reports on those that have been. Cost allocation questions remain open.

The exceptional case path: one example

Some projects continue to use exceptional case filings under the older rules. In Advice Letter 7785-E, filed December 18, 2025, PG&E asked the Commission to approve an agreement to serve Google LLC facilities in San Jose, where forecasted demand at full build is 250 megawatts. The filing shows the sequence: Google applied on March 3, 2025; PG&E completed the latest Preliminary Engineering Study report in December 2025; and PG&E asked for approval by June 1, 2026 so construction could begin by January 2027, with the interconnection facilities expected to be operational by December 2028. The estimated cost of the interconnection work is between $64 million and $137 million including contingencies, with Google building a 230 kV switching station and transferring it to PG&E when complete.

How the state counts the pipeline

The Energy Commission builds utility energization requests into its demand forecast. Its April 15, 2026 methodology memo states that approximately 1,000 megawatts (MW) of existing data center peak demand operated in California as of December 2025. Utilities reported 23,278 MW of requested data center capacity that month (including 2,600 MW of Valley Electric Association requests for sites in Nevada): 5,086 MW with signed service agreements, 9,587 MW in active applications, and 8,604 MW in pre-application inquiries.

The CEC does not treat requests as load. It applies a 67 percent utilization factor and confidence levels by stage, and assumed that projects without signed agreements would not begin service for 3-5 years. PG&E’s own January slides listed 9,600 MW in its data center pipeline as of September 2025: 7,950 MW in application and preliminary engineering, 1,600 MW in final engineering (18 projects), and 50 MW in construction. For the projects in final engineering, the slides stated that 95% of MWs were estimated to be available by 2030 as load ramps over time.

Developers and landowners comparing sites can see how DBMAC approaches power, water, and site analysis on its energy and data centers page.

Approvals beyond the utility

A utility agreement does not entitle a site. Other approvals apply.

For the transmission side of this path, see CAISO large load interconnection, including what the Board approved on October 28, 2026 and the November 16 FERC filing.

What to watch

  • The Rule 30 final decision. The interim rule remains in effect until a subsequent or final decision is issued. That decision addresses refunds, interest, and repayment of Type 4 pre-funding loans. The Q3 2026 target passed without a final decision, and PG&E has asked the Commission to hold the proceeding in abeyance; the Public Advocates Office opposed that request on October 20, 2026.
  • The partial settlement. If adopted, it sets the reporting and CCA coordination rules that apply to applicants. It was still pending on October 20, 2026, when the Public Advocates Office asked the Commission to approve it whether or not the proceeding is stayed.
  • The SB 57 assessment. Signed October 11, 2025, SB 57 (Chapter 647, Statutes of 2025) authorizes the California Public Utilities Commission (CPUC) to assess whether costs from new data center loads shift costs to other customers; any assessment must be reported to the Legislature and posted by January 1, 2027.
  • Data center tariffs in R.26-04-009. SB 886 and AB 2383, signed September 21, 2026, set a January 1, 2028 deadline for new data center tariffs. The Public Advocates Office reports that Track 1 of R.26-04-009 will address data center tariffs, with a proposed decision scheduled before that date. The September 28 article on the new laws covers what they require.
  • The next demand forecast. The CEC’s memo says its assumptions will be revisited and refined in future IEPR forecasts.

Frequently asked questions

What is PG&E Electric Rule 30?

A PG&E tariff for non-residential retail customers served at transmission voltages from 50 kV up to and including 230 kV. PG&E filed it in November 2024 in Application 24-11-007, and the CPUC allowed interim implementation in July 2025 while the rest of the application is decided.

Who pays for transmission upgrades to serve a data center in PG&E territory?

Under the interim rule, the customer pays the full initial costs of Facility Types 1-3 through advances or actual cost payments, and provides 100 percent of Type 4 network upgrade costs as a pre-funded loan. Refunds and repayment of pre-funded loans are deferred to the final decision and are not guaranteed.

How long does data center power interconnection take in California?

It depends on each project's study results and upgrades. In one filed example, Google applied to PG&E on March 3, 2025 for a 250 MW San Jose load, and the interconnection facilities are expected to be operational by December 2028. The CEC assumed projects without signed agreements would not begin service for 3-5 years.

Do data center backup generators need Energy Commission approval?

They can. Backup generating systems between 50 and 100 MW can seek a Small Power Plant Exemption from the CEC's jurisdiction and then proceed with local permitting. The generators also need air district permits; in the Bay Area, the air district issues an Authority to Construct.

Is California creating a special electricity rate for data centers?

Yes. SB 886 (Chapter 438, Statutes of 2026), signed September 21, 2026, requires the CPUC to establish new tariffs or update its electric rules for data centers by January 1, 2028. AB 2383 (Chapter 435, Statutes of 2026) requires investor-owned utilities to file data center tariffs, and community choice aggregators and electric service providers to adopt data center generation tariffs by the same date. According to a Public Advocates Office filing of October 20, 2026, Track 1 of the CPUC's rate design rulemaking, R.26-04-009, will address data center tariffs, with a proposed decision scheduled before January 1, 2028. Separately, SB 57 (Chapter 647, Statutes of 2025) authorized the CPUC to assess whether costs from new data center loads shift costs to other customers, with any assessment due by January 1, 2027. The September 28 article on the seven data center laws covers the details.

Sources

  1. Decision 25-07-039: Decision Partly Granting and Partly Denying Pacific Gas and Electric Company's Motion for Interim Implementation of Electric Rule Number 30 (A.24-11-007) (opens in a new tab)California Public Utilities Commission, Issued July 28, 2025
  2. Advice 7772-E: Modifications to Proposed Electric Rule 30 and Associated Form Agreements in Compliance with Decision 25-07-039 (opens in a new tab)Pacific Gas and Electric Company, December 4, 2025
  3. Advice 7785-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Interconnection for Google LLC (opens in a new tab)Pacific Gas and Electric Company, December 18, 2025
  4. Public Advocates Office Opening Brief, Application 24-11-007 (opens in a new tab)Public Advocates Office, California Public Utilities Commission, October 24, 2025
  5. E-Mail Ruling Establishing New Proceeding Schedule and Ruling on Motions, Application 24-11-007 (opens in a new tab)California Public Utilities Commission, Administrative Law Judge Garrett Toy, February 17, 2026
  6. Joint Motion for Adoption of Partial Settlement Agreement of PG&E, the Public Advocates Office, the California Community Choice Association, and Sierra Club (opens in a new tab)Filed with the California Public Utilities Commission, Application 24-11-007, May 7, 2026
  7. Rate Reducing Load Growth: Unlocking an Affordable & Sustainable Future (presentation to the Assembly Joint Utilities & Energy and Privacy informational hearing) (opens in a new tab)Pacific Gas and Electric Company, posted by the Assembly Utilities and Energy Committee, January 28, 2026
  8. Data Center Methodology Memo: Supporting Document for the 2025 IEPR Forecast (opens in a new tab)California Energy Commission, April 15, 2026
  9. STACK SVY03A Data Center Campus (Docket 23-SPPE-01) (opens in a new tab)California Energy Commission, Accessed July 13, 2026
  10. San Jose Data Center, Notice of Determination (SCH 2021020002) (opens in a new tab)CEQAnet, Governor's Office of Land Use and Climate Innovation, Received May 15, 2026
  11. Legislation to Protect California Ratepayers from Paying for Data Centers' Energy Costs Advances in Legislature (opens in a new tab)Office of Senator Steve Padilla, July 10, 2025
  12. Legislation to Protect California Ratepayers from Paying for Data Centers' Energy Costs Signed into Law (opens in a new tab)Office of Senator Steve Padilla, October 11, 2025
  13. SB 57 (Padilla), Chapter 647, Statutes of 2025: Electrical corporations: data centers: report (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered October 11, 2025
  14. SB 886 (Padilla), Chapter 438, Statutes of 2026: California Technology Innovation and Ratepayer Protection Act (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  15. AB 2383 (Zbur), Chapter 435, Statutes of 2026: Electricity: data centers (chaptered bill text) (opens in a new tab)California Legislative Information, Chaptered September 21, 2026
  16. Public Advocates Office Response in Opposition to Pacific Gas and Electric Company's Motion to Hold Proceeding in Abeyance, Application 24-11-007 (opens in a new tab)Public Advocates Office, California Public Utilities Commission, October 20, 2026
  17. Pacific Gas and Electric Company's Motion to Hold Proceeding in Abeyance (A.24-11-007) (opens in a new tab)Pacific Gas and Electric Company, filed with the California Public Utilities Commission, October 5, 2026

Energy and data centers

Weighing a site for a large load? Start with the power path.

Utility study stages, pre-funding obligations, and generator permits each shape a data center schedule before construction begins. DBMAC Strategies helps developers, landowners, and communities assess power, water, and site readiness and map the approvals a project needs. How DBMAC works on energy and data center projects.

Any matter before a public body on which Daron holds or has held a seat, whether county, regional, or statewide, is reviewed for conflicts before any substantive conversation. See all of his seats.