California data center power interconnection now runs through a set of utility rules that are still being written. For sites in Pacific Gas and Electric Company territory, the governing document is Electric Rule 30, a tariff for retail customers served at transmission voltage, which the California Public Utilities Commission allowed PG&E to use on an interim basis in Decision 25-07-039 while the full application remains open. The interim rule decides who pays for which facilities, what a customer must submit, and what is still undecided.
The utility is only one part of the approval path. This guide covers the utility rules, the timelines the record shows, and the other approvals a project needs. It was first published in mid-July 2026 and updated in October 2026.
Why large loads needed a new rule
Before Rule 30, PG&E had no retail tariff for customers connecting at transmission voltage. Its existing tariffs covered wholesale transmission connections under federal rules and distribution-level service under Electric Rules 15 and 16, but not retail customer energization at transmission levels. Each project was handled as an exceptional case, filed as a Tier 3 advice letter for individual Commission review.
Demand for that kind of service has grown. According to the Public Advocates Office’s opening brief, PG&E stated that it interconnected 24 transmission-level customers between 2014 and 2022, and that in the last two years it received 40 applications, with 75 percent of the requests coming from data centers. In a January 28, 2026 presentation to an Assembly informational hearing, PG&E said Rule 30 would eliminate more than 12 months, covering negotiation plus 9 to 12 months for a Tier 3 advice letter and CPUC approval.
How interim Rule 30 works
The interim tariff applies to non-residential applicants served at transmission voltages from 50 kV up to and including 230 kV, with PG&E deciding the service voltage. Under the application, customers interconnecting above 230 kV would use exceptional case filings.
The four facility types
The decision sorts interconnection work into four types: dedicated transmission service facilities (Type 1), substation or switching station interconnection upgrades (Type 2), interconnection network upgrades that adapt the network to serve the customer (Type 3), and transmission network upgrades to the existing grid (Type 4). Under the interim rule, customers provide the full initial costs of Facility Types 1-3 through advances or actual cost payments, and Type 4 work is eligible when the customer provides 100 percent of the project cost as a pre-funded loan.
PG&E’s first compliance tariff was rejected by the Energy Division Director on November 19, 2025. The replacement, Advice Letter 7772-E, filed December 4, 2025, states that the applicant shall provide a pre-funding loan for 100 percent of the actual costs of all Type 4 upgrades its request causes, with repayment left to the Commission’s final decision.
What is deferred
The interim decision deferred refunds of advances and actual cost payments to the final decision, and states that no interest will accrue on funds advanced while the interim rule is in effect. Contracts signed under the interim rule stay in place if Rule 30 later changes, but remain subject to the final decision on refunds, interest, and loan repayment.
What an applicant provides
The tariff requires an applicant to include a forecast of expected load for the first ten (10) years of service, and to provide land rights on its own premises at no cost to PG&E. The form agreement ties the estimated in-service date to PG&E’s Preliminary Engineering Study report and lists the conditions that can move it, including scope changes and late payment of invoices. Where the site is inside a community choice aggregator’s territory, PG&E must send the CCA a copy of the application within 20 business days of receiving it.
Key details and timeline
- November 21, 2024: PG&E filed Application 24-11-007 proposing Rule 30, according to the interim decision.
- July 28, 2025: The Commission issued Decision 25-07-039, partly granting interim implementation.
- December 4, 2025: PG&E filed the revised interim tariff in Advice Letter 7772-E.
- January 28, 2026: PG&E told the Assembly hearing that the proceeding had been delayed, with a new goal of resolution no later than Q3 of 2026.
- February 17, 2026: An administrative law judge set a new schedule, with opening briefs due May 8 and reply briefs due May 22, 2026.
- May 7, 2026: PG&E, the Public Advocates Office, the California Community Choice Association, and Sierra Club asked the Commission to adopt a partial settlement that resolves reporting and information sharing issues only.
- September 3, 2026: Decision 26-09-016 extended the proceeding’s statutory deadline to February 26, 2027.
- October 5, 2026: PG&E moved to hold the proceeding in abeyance until its revised transmission owner tariff at the Federal Energy Regulatory Commission is final and effective. On October 20, the Public Advocates Office opposed the motion and asked the Commission to issue a decision. As of October 27, 2026, the Commission had not ruled on the motion or issued a final decision, and PG&E’s goal of resolution by Q3 2026 had passed.
Under that settlement, PG&E would provide quarterly reports on transmission-level customers that have applied but are not yet energized, and annual reports on those that have been. Cost allocation questions remain open.
The exceptional case path: one example
Some projects continue to use exceptional case filings under the older rules. In Advice Letter 7785-E, filed December 18, 2025, PG&E asked the Commission to approve an agreement to serve Google LLC facilities in San Jose, where forecasted demand at full build is 250 megawatts. The filing shows the sequence: Google applied on March 3, 2025; PG&E completed the latest Preliminary Engineering Study report in December 2025; and PG&E asked for approval by June 1, 2026 so construction could begin by January 2027, with the interconnection facilities expected to be operational by December 2028. The estimated cost of the interconnection work is between $64 million and $137 million including contingencies, with Google building a 230 kV switching station and transferring it to PG&E when complete.
How the state counts the pipeline
The Energy Commission builds utility energization requests into its demand forecast. Its April 15, 2026 methodology memo states that approximately 1,000 megawatts (MW) of existing data center peak demand operated in California as of December 2025. Utilities reported 23,278 MW of requested data center capacity that month (including 2,600 MW of Valley Electric Association requests for sites in Nevada): 5,086 MW with signed service agreements, 9,587 MW in active applications, and 8,604 MW in pre-application inquiries.
The CEC does not treat requests as load. It applies a 67 percent utilization factor and confidence levels by stage, and assumed that projects without signed agreements would not begin service for 3-5 years. PG&E’s own January slides listed 9,600 MW in its data center pipeline as of September 2025: 7,950 MW in application and preliminary engineering, 1,600 MW in final engineering (18 projects), and 50 MW in construction. For the projects in final engineering, the slides stated that 95% of MWs were estimated to be available by 2030 as load ramps over time.
Developers and landowners comparing sites can see how DBMAC approaches power, water, and site analysis on its energy and data centers page.
Approvals beyond the utility
A utility agreement does not entitle a site. Other approvals apply.
- Energy Commission jurisdiction over backup power. The Small Power Plant Exemption lets applicants with thermal plants between 50 and 100 MW obtain an exemption from the CEC’s jurisdiction and proceed with local permitting. The STACK SVY03A campus in Hayward, for example, received an exemption for backup generators totaling up to 76.6 MW.
- Air district permits. Generators also need air district approval. A Notice of Determination posted May 15, 2026 for a San Jose data center records that the Bay Area Air Quality Management District has already issued Authority to Constructs for 140 natural gas backup generators there. In that record the Energy Commission is the CEQA lead agency and the air district a responsible agency.
- Local permitting. Once the CEC grants an exemption, the project proceeds with local permitting through the city or county.
For the transmission side of this path, see CAISO large load interconnection, including what the Board approved on October 28, 2026 and the November 16 FERC filing.
What to watch
- The Rule 30 final decision. The interim rule remains in effect until a subsequent or final decision is issued. That decision addresses refunds, interest, and repayment of Type 4 pre-funding loans. The Q3 2026 target passed without a final decision, and PG&E has asked the Commission to hold the proceeding in abeyance; the Public Advocates Office opposed that request on October 20, 2026.
- The partial settlement. If adopted, it sets the reporting and CCA coordination rules that apply to applicants. It was still pending on October 20, 2026, when the Public Advocates Office asked the Commission to approve it whether or not the proceeding is stayed.
- The SB 57 assessment. Signed October 11, 2025, SB 57 (Chapter 647, Statutes of 2025) authorizes the California Public Utilities Commission (CPUC) to assess whether costs from new data center loads shift costs to other customers; any assessment must be reported to the Legislature and posted by January 1, 2027.
- Data center tariffs in R.26-04-009. SB 886 and AB 2383, signed September 21, 2026, set a January 1, 2028 deadline for new data center tariffs. The Public Advocates Office reports that Track 1 of R.26-04-009 will address data center tariffs, with a proposed decision scheduled before that date. The September 28 article on the new laws covers what they require.
- The next demand forecast. The CEC’s memo says its assumptions will be revisited and refined in future IEPR forecasts.