California STIP programming decides which state highway, local road, transit, and active transportation projects receive a share of the state’s transportation capital dollars, and in which year. The State Transportation Improvement Program (STIP) is adopted by the California Transportation Commission (CTC) every two years, and the 2026 STIP was adopted on March 19, 2026. For counties, cities, transit operators, and regional agencies, each cycle turns on a short list of documents: the fund estimate, the STIP Guidelines, the regional transportation improvement programs (RTIPs), and the Commission’s adoption.
What the STIP is and how the money is divided
The CTC describes the STIP as a key planning document for funding state highway and local road, intercity rail and transit, and active transportation improvements throughout California. Under the 2026 STIP Guidelines, the STIP is adopted no later than April 1 of each even-numbered year, covers a five-year period, and adds two new years of programming capacity each cycle. The 2026 STIP added 2029-30 and 2030-31 to the commitments carried forward from the 2024 STIP.
New STIP funding is split between two programs. According to the guidelines, 75 percent funds the regional program, which is divided by formula into county shares, and 25 percent funds the interregional program, which Caltrans nominates through its Interregional Transportation Improvement Program (ITIP). County shares are available solely for projects that regions nominate in their RTIPs. The guidelines state that the shares are calculated with the statutory formula, which considers population and center highway lane miles.
The two-year cycle, step by step
The STIP calendar alternates between odd and even years. The guidelines set out each step:
- Fund estimate (odd years). Caltrans submits a proposed fund estimate by July 15, and the Commission adopts it by August 15 of the same year.
- Guidelines. The Commission may amend the STIP Guidelines after a public hearing, but not between thirty days after fund estimate adoption and STIP adoption.
- RTIPs (December 15 of odd years). Each regional agency, after consulting with Caltrans, adopts its RTIP and submits it to the Commission and Caltrans no later than December 15.
- Hearings and staff recommendations. The Commission holds STIP hearings in the north and south. State law requires the Executive Director to release staff recommendations at least 20 days prior to adoption.
- Adoption (before April 1 of even years). The Commission adopts the five-year STIP and submits it to the Legislature and the Governor.
For the 2026 STIP, the Commission adopted the fund estimate and guidelines on August 14-15, 2025. Regions submitted RTIPs and Caltrans submitted its final ITIP on December 15, 2025. The Commission held hearings on January 28 and February 5, 2026, published staff recommendations on February 27, 2026, and adopted the STIP on March 19, 2026. On the same statutory calendar, the next fund estimate and RTIP round fall in 2027, an odd-numbered year, ahead of a 2028 STIP.
The fund estimate sets the ceiling
Every STIP is sized to its fund estimate. The guidelines provide that the total amount programmed in each fiscal year of the STIP shall not exceed the amount specified in the fund estimate. The 2026 fund estimate covered 2026-27 through 2030-31 and estimated total statewide new programming capacity of $1.085 billion: $1.358 billion in the State Highway Account and negative $273 million in the Public Transportation Account. With $1.625 billion carried forward from the 2024 STIP, total programming came to $2.710 billion.
Three features of the 2026 estimate shaped what regions could propose:
- Timing. Most new capacity fell in the two added years. The fund estimate also identified negative programming capacity of $133 million carried over from 2025-26, which left net available capacity of $951.6 million.
- Transit eligibility. Because Public Transportation Account capacity was negative, rail and transit projects in the 2026 STIP had to be eligible for State Highway Account or Federal funds.
- No minimum. The 2026 fund estimate set no Base (Minimum) target, and the guidelines state that the Total Target is not a minimum, guarantee, or limit on nominations or project selection.
Demand exceeded early-year capacity. Proposals for the first three years of the STIP period exceeded the capacity available by $333 million, and the adopted STIP moved some projects to later years.
County shares in the San Joaquin Valley
The Commission’s 2026 STIP county share tables list a Total Target through 2030-31 for every county, in thousands of dollars. Fresno’s was 14,611; Kern’s, 26,371; Madera’s, 4,535; Merced’s, 4,834; San Joaquin’s, 10,370; and Stanislaus’s, 8,876. Kings and Tulare showed zero, the result the tables give when new capacity is insufficient to cover prior advances. Statewide, the regional total was 781,778 and the interregional share 169,872.
What it takes to get a project programmed
There are two doors into the STIP. The Commission includes in the STIP only projects nominated by a regional agency in its RTIP or by Caltrans in its ITIP. A city, county, or transit operator with a candidate project works through its regional transportation planning agency and that agency’s selection process. The guidelines set several requirements before nomination:
- A project study report. A PSR or PSR equivalent is required for all new projects. It must define and justify scope, cost, and schedule to the satisfaction of the regional agency and Caltrans, and a registered engineer must prepare it.
- Consistency with the regional plan. Each RTIP must be based on the regional transportation plan and, where applicable, the Sustainable Communities Strategy. The 2026 STIP did not include one multi-county interregional corridor project because it was not included in an adopted Regional Transportation Plan.
- Full funding by phase. The Commission does not program a phase of a project without a full funding commitment. For 2026, uncommitted funds were accepted only from four state programs (the Solutions for Congested Corridors Program, the Trade Corridor Enhancement Program, the Local Partnership Program, and the Active Transportation Program) and from federal discretionary programs, with deletion if the commitments were not secured on time.
- Components. Listings specify costs for four components: permits and environmental studies; plans, specifications, and estimates; right-of-way; and construction.
A region may program up to five percent of the county share for planning, programming, and monitoring. A region for a county with a population under one million may ask to advance future share for a larger project, up to 200 percent of the county share for the share period extending beyond the STIP.
Kern Council of Governments’ 2026 RTIP, adopted November 20, 2025, shows how a region uses its share. It requested $25,371,000 in 2029-30 and 2030-31 for SR 58 Truck Climbing Lane Phase 2, to meet the match requirement for future TCEP and BUILD applications. Agencies working out how STIP shares fit alongside SB 1 and federal grants can see how DBMAC approaches program matching and local match on its public funding and infrastructure page.
After adoption: allocation and delivery deadlines
Programming is a commitment, not money in hand. Each component still needs a Commission allocation, and the guidelines’ timely use of funds rules apply:
- Allocation. For locally implemented projects, programmed funds are available for allocation until June 30th of the fiscal year in which they are programmed. Funds not allocated by then lapse and are deleted from the STIP.
- Contract award. Construction funds must be encumbered by the award of a contract within six months of allocation.
- Expenditure and completion. Local environmental, design, and right-of-way funds must be spent by the end of the second fiscal year after allocation, and the agency has up to 36 months after award to accept the construction contract.
- Extensions. No deadline may be extended more than once. Each extension is capped at 20 months and requires an unforeseen and extraordinary circumstance, and requests go to the Caltrans district at least 60 days before the deadline.
That calendar made June 2026 a working month for sponsors. Funds programmed for 2025-26 reached their allocation deadline on June 30, 2026, and under the 60-day rule, which requires extension requests at least 60 days before the deadline, the last day to request an extension of that deadline was May 1, 2026.
What to watch
- Allocation conditions. The adopted STIP notes that if funding is less than assumed, the Commission may be forced to delay or restrict allocations through allocation plans; if it is greater, some projects may be allocated sooner than programmed.
- Delivering early. An AB 3090 amendment lets a local agency deliver a STIP project with its own funds ahead of the programmed year, with the capacity later programmed as a cash reimbursement or a replacement project.
- The 2028 cycle. A project not yet in the STIP needs a PSR or equivalent and consistency with the regional plan before its region can nominate it in the next RTIP round.