Energy and Utilities

CEC Opt-In Permitting Process: How AB 205 Certification Works for Clean Energy Projects

AB 205 lets eligible solar, wind, storage, geothermal, hydrogen, and clean energy manufacturing projects seek a single permit from the California Energy Commission. Here is who qualifies, how the 270-day review runs, and what the first decisions show.

Daron McDaniel

By Principal, DBMAC Strategies

Published Last updated 8 min read

The CEC opt-in permitting process gives developers of large solar, wind, battery storage, geothermal, clean hydrogen, and clean energy manufacturing projects a way to have the California Energy Commission, rather than a city or county, permit their facility. Created by Assembly Bill 205 (2022), the Opt-In Certification Program makes the CEC the lead agency for environmental review and lets it issue a certificate that is in lieu of any local permit or local law or ordinance and most, but not all, state permits. This guide explains who qualifies, how the 270-day review works, what the CEC must find to approve a project, what it costs, and what the first decisions show.

What the opt-in program is

The CEC already holds exclusive permitting authority over thermal power plants 50 MW and larger. AB 205 added a separate, voluntary path for clean energy facilities. The CEC’s fact sheet calls it an optional permitting process through which developers can submit project applications. The Commission’s pre-filing presentation summarizes the main features: filing is optional, there is no evidentiary proceeding, the CEC has a 270-day period to reach a decision, and the program is in effect until June 30, 2030.

The governing provisions are in Chapter 6.2 of Division 15 of the Public Resources Code and California Code of Regulations, title 20, sections 1875 through 1882.

Which projects are eligible

According to the CEC’s April 2026 fact sheet and its pre-filing presentation, these facilities can apply:

  • Solar photovoltaic or terrestrial wind power plants of 50 megawatts (MW) or more.
  • Energy storage systems capable of storing 200 megawatt-hours (MWh) or more.
  • Stationary power plants of 50 MW or more using thermal energy other than fossil or nuclear fuels, and geothermal of any size.
  • Certain transmission lines associated with those generating and storage facilities.
  • Specified facilities that manufacture or assemble clean energy or storage technologies or related components.
  • Hydrogen production facilities not derived from fossil fuel feedstock, with associated onsite storage and processing.

How the CEC opt-in permitting process works, step by step

Before filing

An applicant meets with CEC staff at least 30 days before filing the application, and the CEC is required to invite the local government to attend that mandatory pre-filing meeting. Under memorandums of understanding, the Department of Fish and Wildlife, the Water Boards, and the Department of Toxic Substances Control may also take part. Battery storage applicants have an added step: under Public Resources Code section 25545.19, they must certify that at least 30 days before applying they met and conferred with the authority that has jurisdiction over fire suppression in the area and sought input on emergency action plans.

Completeness review

Fees are submitted with the application. Staff then have 30 days to conduct application completeness review, can request missing information, and have 45 days to review supplemental material. The notice and application are shared with local government, other public agencies, and tribes. The review schedule runs from the day the application is deemed complete.

The 270-day environmental review

The CEC prepares an environmental impact report (EIR), mitigated negative declaration, or negative declaration under CEQA. The fact sheet lists the milestones, counted from the completeness determination:

  • Day 3: Notice of Preparation of an EIR, if applicable.
  • Day 5: Invitations to request tribal consultation.
  • Day 30: Public meeting as close as practicable to the project site.
  • Day 150: Staff Assessment, which includes the draft environmental document; the public comment period begins.
  • Days 180 to 210: Public meeting on the Staff Assessment near the site; comments close at Day 210, 60 days after publication.
  • Day 240: Updated Staff Assessment and the executive director’s recommendation.
  • Day 270: CEC business meeting, where commissioners can approve or disapprove the project or require more information.
  • Day 360: State agencies retaining permit authority make permit decisions.

The CEC notes that these deadlines are subject to any substantial changes made to the project by the developer or certain other events. Its FAQ adds that new significant effects identified after the draft document is published, requiring additional public comment, can affect the 270-day decision.

What the CEC must find to approve a project

Opt-in certification adds conditions beyond CEQA. The CEC must find that the applicant has entered into a community benefits agreement and has certified payment of prevailing wage, or equivalent, and use of a skilled and trained workforce, or equivalent, for all construction. The pre-filing presentation also lists a finding of net positive economic benefit to the local government that would have had permitting authority, described as a rebuttable presumption. For significant environmental effects that cannot feasibly be avoided or mitigated, the CEC must adopt a statement of overriding considerations before approving.

Which permits the certificate replaces, and which it does not

The certificate replaces the local land use permit and most state permits. According to the CEC’s FAQ, it will not supersede the permitting requirements of the California Coastal Commission or the San Francisco Bay Conservation and Development Commission within their jurisdictions, or the permits of the applicable Regional Water Quality Control Board. For manufacturing facilities, local air district and DTSC permits also remain. Agencies that keep permitting authority must issue permits within 90 days of a CEC decision. Projects on federal land also need federal approval: the Soda Mountain project was approved contingent on BLM approval.

Fees and post-approval costs

The pre-filing presentation lists a $750,000 nonrefundable licensing application deposit, with the CEC invoicing the applicant for actual costs above that amount. If a certificate is issued, the owner pays a $70,000 annual compliance fee, first on the decision date and then each July 1, and a $5,000 fee with each post-certification petition. A Delegate Chief Building Official arrangement is negotiated with the project owner as a separate cost. Local agencies can be reimbursed for eligible review costs under title 20, section 1878.1, through approved budgets and invoices.

What the first decisions show

  • Darden Clean Energy Project, Fresno County (June 2025). The first project permitted under the program pairs a 1,150 MW solar facility with up to 1,150 MW (4,600 MWh) of battery storage. The CEC said it will be built on 9,500 acres of land in western Fresno County that can no longer support agricultural production, with $2 million in community investments over the next decade.
  • Fountain Wind, Shasta County (December 2025). Commissioners voted unanimously to deny the project, following their staff’s recommendation, Jefferson Public Radio reported. Shasta County’s Planning Commission and Board of Supervisors had denied the project earlier.
  • Soda Mountain Solar, San Bernardino County (April 2026). The second renewable energy project approved through the program: up to 300 MW of solar and 300 MW of storage on about 2,670 acres of BLM-administered land, with a $50,000 community benefits commitment.
  • Potentia-Viridi, eastern Alameda County (May 2026). A 400 MW battery system able to discharge up to 3,200 MWh. The developer signed two community benefits agreements providing $925,000 to two community groups.

In its May 26, 2026 release, the CEC said it had approved three projects totaling roughly 3,300 megawatts through the program in the prior year.

Who is affected

  • Developers choosing between local entitlement and a single state process with a fixed review schedule, a deposit, and community benefits and labor conditions.
  • Counties and cities. They are invited to the pre-filing meeting, can be reimbursed for eligible costs, and an approved certificate is in lieu of any local permit. The CEC states it will analyze compliance with local laws and attempt to resolve non-compliance when possible.
  • Tribes. The CEC must send consultation requests within five days of an application being deemed complete and take all feasible measures to avoid or minimize adverse effects to tribal cultural resources.
  • Community organizations, which can be parties to the legally binding agreements the CEC requires with, or that benefit, a coalition of one or more community-based organizations.
  • Landowners whose property hosts a proposed facility, such as the former farmland at the Darden site.

Pending rule changes (added October 27, 2026)

The CEC has opened an emergency rulemaking, Docket 26-OIR-04, to amend its opt-in regulations (Title 20, California Code of Regulations, sections 1875 to 1882 and Appendix B) for Senate Bills 254 and 283, enacted in 2025. According to the CEC’s workshop notice, the proposed changes would incorporate the statutory presumption of net economic benefits and new requirements for applicants to provide evidence of property rights to the proposed location and of consultation with the fire suppression authority. They would also clarify procedures for suspending or ending an application early, restructure local agency reimbursement, refine the community benefits agreement process, address changes in project ownership or operational control after certification, and update the Appendix B information requirements.

The CEC rescheduled the remote workshop to November 2, 2026, from 1:00 to 4:00 p.m., and written comments are due by 5:00 p.m. on November 10, 2026. The steps in this guide follow the current regulations; sponsors preparing a filing should check the docket for the adopted text.

What to watch on an opt-in project

The opt-in record is built in public: a project docket, a Day 30 meeting near the site, a 60-day comment period on the Staff Assessment, and a decision at a noticed business meeting. Much of what shapes the schedule happens before the clock starts, including the pre-filing meeting, fire authority consultation for storage, and negotiation of community benefits agreements. For local agencies, the pre-filing meeting and the comment period are the points where local conditions enter the record. Sponsors and agencies weighing the opt-in path against a local entitlement can see how DBMAC approaches approval path mapping, staff reports, and hearings on its government affairs page.

The CEC’s fact sheet points to its Opt-In Certification Program web page for program details and for signing up to receive information about a specific project.

Frequently asked questions

Which projects qualify for the CEC opt-in permitting process?

Solar photovoltaic or terrestrial wind plants of 50 MW or more, energy storage systems of 200 MWh or more, non-fossil thermal plants of 50 MW or more, geothermal plants, associated transmission lines, specified clean energy manufacturing facilities, and hydrogen production not derived from fossil fuel feedstock, according to the CEC's Opt-In Certification fact sheet.

Can the CEC approve a project that a county has denied?

Yes. The CEC's FAQ states that an approved certificate is in lieu of any local permit or local law or ordinance under Public Resources Code section 25545.1(b)(1). The CEC still analyzes compliance with local laws, attempts to resolve non-compliance when possible, and must invite the local government to the mandatory pre-filing meeting.

How long does CEC opt-in certification take?

The CEC must decide within 270 days of deeming an application complete, subject to exceptions for substantial project changes and certain other events. Before that clock starts, the pre-filing meeting comes at least 30 days before filing, followed by a 30-day completeness review. Agencies that keep permitting authority act by Day 360.

What does it cost to apply for opt-in certification?

The CEC lists a $750,000 nonrefundable deposit submitted with the application, with actual costs above that amount invoiced to the applicant. Approved projects pay a $70,000 annual compliance fee and $5,000 with each post-certification petition. Community benefits, prevailing wage, and skilled workforce commitments are separate requirements.

Sources

  1. Opt-In Certification Program Fact Sheet (opens in a new tab)California Energy Commission, April 2026
  2. Opt-In Certification FAQs (opens in a new tab)California Energy Commission, April 2026
  3. Opt-In Certification Program Overview: Pre-Filing Meeting (opens in a new tab)California Energy Commission, Siting, Transmission, and Environmental Protection Division, April 2026 (Rev 4-2026)
  4. CEC Approves World's Largest Solar + Battery Storage Project in Fresno County Under Accelerated Permitting Program (opens in a new tab)California Energy Commission, June 12, 2025
  5. CEC Approves Soda Mountain Solar and Battery Storage Project in San Bernardino County (opens in a new tab)California Energy Commission, April 27, 2026
  6. CEC Approves Third Major Clean Energy Project Under Opt-In Certification Program (opens in a new tab)California Energy Commission, May 26, 2026
  7. California Energy Commission kills the Fountain Wind project in Shasta County (opens in a new tab)Jefferson Public Radio, December 22, 2025
  8. UPDATED Notice of Remote-Only Opt-In Certification Program Rulemaking Workshop (Docket 26-OIR-04, TN 273051) (opens in a new tab)California Energy Commission, October 6, 2026

Energy and data centers

Weighing the CEC opt-in path for a clean energy project? Map the approvals first.

Opt-in certification moves the permit decision to the California Energy Commission, but local agencies, tribes, fire authorities, and community groups still shape the record. DBMAC Strategies helps developers, landowners, and local agencies map the approval path, prepare for public meetings, and coordinate with the agencies involved. How DBMAC works on energy and data center projects.

Any matter before a public body on which Daron holds or has held a seat, whether county, regional, or statewide, is reviewed for conflicts before any substantive conversation. See all of his seats.