For a housing developer or landowner, the first question on an urban site is often whether the project needs an environmental impact report at all. Since mid-2025, the CEQA exemption for infill housing in Public Resources Code Section 21080.66 can give qualifying California projects a different answer. On June 30, 2025, the Governor signed AB 130 and SB 131, two budget trailer bills that the Governor’s Office said would streamline California Environmental Quality Act review to speed up delivery of housing and infrastructure projects. AB 130 created the urban infill housing exemption, and SB 131 added a “near miss” path for housing projects that fail one condition, according to a September 2025 staff briefing at the San Francisco Bay Conservation and Development Commission (BCDC). Eligibility is decided by the lead agency on its own record, so the details below come from checklists, notices, and briefings that California public agencies have published.
What changed in 2025
The Governor’s Office said the package streamlines review for infill housing, high-speed rail facilities, utilities, broadband, community-serving facilities, and other project types. SB 131 also exempts rezoning that implements the schedule of actions of an approved housing element, with exceptions for distribution centers, oil and gas infrastructure, and natural or protected lands.
The statute has already been amended. On October 11, 2025, the Governor signed SB 158, which amended several sections enacted by AB 130 and SB 131, according to the County of San Mateo. Lead agencies are using the exemption: the City of Mountain View filed a Notice of Exemption citing Section 21080.66, received on March 26, 2026, for 323 added apartment units on a 14.5-acre residential site.
Which projects qualify for the statutory infill exemption
The City of San Diego’s Section 21080.66 checklist for a project called City View walks through each condition. The main tests are:
- Project type. A housing development project: residential units only, transitional or supportive housing, farmworker housing, or a mixed-use project where at least two-thirds of the new or converted square footage is residential. A mixed-use project with at least 500 net new residential units and no hotel or other transient lodging can also qualify with at least 50 percent residential square footage.
- Site size. Not more than 20 acres. For a builder’s remedy project, Public Resources Code Section 21080.66(a)(1)(B) limits the project site or parcel to not more than four acres.
- Location. Within an incorporated municipality or an urban area as defined by the U.S. Census Bureau.
- Infill setting. The site was previously developed with an urban use, or at least 75% of the perimeter of the site adjoins parcels developed with urban uses, or at least 75 percent of the area within a quarter-mile radius is developed with urban uses, or, for a site with four sides, at least three of the four sides are developed with urban uses and at least two-thirds of the perimeter adjoins parcels developed with urban uses (Section 21080.66(a)(3)(D), as amended by SB 158, effective October 11, 2025).
- Plan and zoning consistency. Consistent with the general plan, zoning ordinance, and any local coastal program. A density bonus, waivers, or reduced parking under Government Code Section 65915 are not grounds for finding a project inconsistent.
- Density. At least one-half of the applicable density in Government Code Section 65583.2(c)(3)(B), which ranges from 10 units per acre for some unincorporated areas in nonmetropolitan counties to 30 units per acre for a jurisdiction in a metropolitan county.
Sites and conditions that disqualify a project
The exemption incorporates the site exclusions in Government Code Section 65913.4(a)(6). Under that section, a project cannot be located on:
- Prime farmland or farmland of statewide importance as mapped by the Department of Conservation, or land protected for agriculture by a local ballot measure. Sponsors of edge-of-town sites in farming regions should check the Important Farmland maps early.
- Wetlands, certain coastal zone areas, flood hazard areas or floodways, very high fire hazard severity zones, hazardous waste sites, or earthquake fault zones, subject to the exceptions the statute names.
- Lands identified for conservation in an adopted conservation plan, habitat for protected species, or lands under conservation easement.
The project also may not require demolition of a historic structure placed on a national, state, or local register before a preliminary application was submitted, and, for a project deemed complete on or after January 1, 2025, no portion may be designated as a hotel, motel, or other transient lodging.
Obligations that remain after the exemption
An exemption removes the environmental document, not every requirement. Section 21080.66 itself attaches these conditions:
- Tribal consultation. The local government notifies affiliated tribes, generally within 14 days of the application being deemed complete, or, for applications deemed complete before July 1, 2026, within 14 days of the local government being notified that the project is eligible for the exemption (Section 21080.66(b)(1)(A)). Tribes then have 60 days to accept the invitation to consult; if one does, the local government initiates consultation within 14 days, and it concludes within 45 days, with one possible 15-day extension (Section 21080.66(b)(2) and (b)(3)).
- Phase I assessment. The applicant must complete a phase I environmental assessment as a condition of approval, and any release of a hazardous substance must be addressed before a certificate of occupancy issues.
- Freeway proximity. Housing within 500 feet of a freeway needs a centralized HVAC system with intakes facing away from the freeway, filtration with a minimum efficiency reporting value of 16, and no balconies facing the freeway.
- Labor standards. Prevailing wages apply where 100 percent of the units are dedicated to lower income households, and additional labor standards apply to buildings over 85 feet.
AB 130 also set a decision deadline: 30 days for lead agencies to approve or disapprove complete permit applications for projects exempt under the infill exemption, counted after tribal consultation is complete. Because consultation starts that clock, the tribal notice date is a schedule milestone.
How the Class 32 categorical exemption compares
The statutory exemption sits alongside the Class 32 in-fill exemption in CEQA Guidelines Section 15332. A May 27, 2026 City of San Diego determination for a 1.62-acre site shows its conditions: plan and zoning consistency; a site within city limits of no more than 5 acres, substantially surrounded by urban uses; no habitat value for endangered, rare, or threatened species; no significant traffic, noise, air quality, or water quality effects; and adequate utilities and services. The statutory exemption allows larger sites, and BCDC staff described it as by and large defined by objective criteria.
When a project misses by one condition
SB 131 added Public Resources Code Section 21080.1(b). For a qualifying housing development project that meets a statutory exemption or a listed categorical exemption, including Class 32, except for a single condition, environmental review shall be limited to the environmental effects resulting from that single condition. BCDC staff noted that this review does not need to discuss alternatives and does not apply where two or more conditions make a project ineligible, to projects with a distribution center or oil and gas infrastructure, or on natural or protected lands.
San Diego’s City View project shows the sequence. The sponsor proposes to construct 122 residential units, including 13 affordable units, on a 5.52-acre site designated and zoned for commercial use, which requires a general plan amendment and rezone. The city’s checklist found the project met the other conditions, including density at 22.6 units per acre and a tribal consultation that concluded on May 6, 2026. Because of the zoning inconsistency, it does not qualify for a statutory exemption, so the city also evaluated it on a near-exempt checklist.
Exemptions beyond housing
SB 131 also created or expanded exemptions for other project types. BCDC staff listed farmworker housing, sewer service projects for disadvantaged communities, community water systems, wildfire risk reduction, broadband in a right-of-way, parks and trails, clinics, food banks, advanced manufacturing, and high-speed rail development and maintenance facilities. Each carries its own conditions.
Water districts, counties, and employers can review those exemptions against current capital plans. Matching a project to the right exemption, and building the record staff will rely on, is part of the approval path work described on DBMAC’s government relations page.
What to watch: documenting and defending the exemption
- Build the file the checklist asks for. In its City View findings, San Diego staff cited a title report, a historic review, FEMA flood maps, the Important Farmland Finder, a hazardous site database search, and the tribal consultation record.
- File the Notice of Exemption. Under Public Resources Code Section 21167(d), filing it starts a 35-day statute of limitations on court challenges; if no notice is filed, the period is 180 days.
- Know the local appeal window. In San Diego, a staff exemption determination can be appealed to the City Council within ten (10) business days of the posted notice.
- Track amendments. SB 158 has already changed parts of the package. Confirm the current statute and the lead agency’s current checklist before relying on any summary.