CPUC integrated resource plan filings were due on August 10, 2026. Under a March 20, 2026 ruling in Rulemaking 25-06-019, every load-serving entity (LSE) under the California Public Utilities Commission’s integrated resource planning purview must file and serve its individual integrated resource plan (IRP) by no later than August 10, 2026. The same ruling allowed any party to file initial comments on any or all of those plans by September 21, 2026.
The plans are where each utility, community choice aggregator, and electric service provider shows how it will meet its share of the state’s electricity goals. The Commission then aggregates them and decides which resource portfolios to recommend for transmission planning. For developers, landowners, and counties, that chain feeds the studies that determine where new generation and storage can connect.
What happened
The filing date moved twice. The scoping memo originally set May 5, 2026. An Administrative Law Judge’s ruling dated January 16, 2026 moved the date to June 1, 2026 and set out the requirements LSEs must follow. Then, according to the March 20 ruling, an email ruling issued March 9, 2026 moved the due date to August 10, 2026 in response to a request for delay from several parties. The March 20 ruling confirmed that date, stated that all filing requirement materials were finalized and posted on the Commission’s website, and set the September 21 comment deadline.
Plans filed on August 10 follow the structure the rulings require. Central Coast Community Energy (3CE), for example, filed its 2026 IRP dated August 10, 2026 with a verification, its narrative template, a public version of its Resource Data Template, and its emissions calculator, and asked the Commission to certify the plan. 3CE posted a redacted Resource Data Template publicly and filed a motion to submit the confidential version under seal.
What each plan must contain
The January 16 ruling sets the requirements. It applies to LSEs subject to the Commission’s IRP purview under Public Utilities Code Section 454.52, a group that includes the investor-owned utilities, community choice aggregators, and electric service providers. Small and multi-jurisdictional utilities such as PacifiCorp, Bear Valley Electric, and Liberty Utilities file non-standard plans. The core elements of a standard plan are:
- Common inputs and assumptions. LSEs must use the latest inputs and assumptions staff developed for this cycle, including a load forecast based on the California Energy Commission’s 2024 Integrated Energy Policy Report (IEPR).
- A conforming portfolio. Each LSE must submit at least one conforming portfolio that meets its proportional share of the electric sector greenhouse gas target, which the ruling sets at a 25 million metric ton limit in 2035 and 8 million metric tons by 2045, aligned with the statewide trajectory in the California Air Resources Board’s 2022 Scoping Plan. An LSE may also submit a “preferred” portfolio that goes beyond its assigned targets.
- Assigned load forecasts and GHG benchmarks. The CEC revised the forecasts LSEs submitted, using the 2024 IEPR as the reference case. The ruling notes that PG&E, SCE, and SDG&E had pointed out that many community choice aggregator forecasts did not account for increased data center load projections.
- A narrative template. LSEs must describe their approach to disadvantaged communities and local air emissions, potential cost and rate impacts, and an action plan that includes procurement activities and lessons from prior cycles.
- Data tools. Each LSE also submits a Clean System Power calculator, which estimates greenhouse gas and criteria pollutant emissions and demonstrates compliance with the LSE’s emissions allocation, and a Resource Data Template listing its resources.
The statewide picture behind the plans
To guide individual plans, Commission staff ran a least-cost scenario in the RESOLVE capacity expansion model. The corrected results table in the March 20 ruling shows 28.1 gigawatts of new solar selected by 2030 and 82.7 gigawatts by 2045, along with 6.4 gigawatts of new 8-hour lithium-ion batteries and 2.4 gigawatts of new geothermal by 2030. According to the January ruling, 70 percent of the selected builds are solar and battery storage, and the model selected Path 26 and Path 15 expansions, primarily to increase import capability into Northern California.
Procurement is also already ordered. At its February 26, 2026 voting meeting, the Commission required electricity providers under its jurisdiction to procure 6,000 megawatts of new clean energy and storage net qualifying capacity, and the Commission’s release states that fossil fuel generation cannot be used to meet the requirement. Decision 26-02-057 requires 2,000 megawatts online by June 1, 2030, another 2,000 megawatts by June 1, 2031, and a third 2,000 megawatts by June 1, 2032. At least one-quarter of the procurement by June 1, 2032 must come from resources with clean firm attributes (capacity factors of at least 80 percent and not use-limited) or long-duration storage able to discharge for at least eight hours. Utility Dive reported that the Commission voted unanimously and that PG&E’s share is an additional 1,077 megawatts by 2032.
How the plans connect to transmission and interconnection
The IRP record does not stay at the Commission. The January ruling states that, in aggregating the individual filings, the Commission may make different or additional policy choices before adopting the next Preferred System Plan or recommending portfolios for transmission planning. Decision 26-02-057 itself transmitted a base case portfolio and a sensitivity portfolio to the California Independent System Operator (CAISO) for its 2026-2027 Transmission Planning Process, with the base case extending online dates for some offshore wind resources by up to six years.
CAISO’s side of the exchange was updated this summer. On July 15, 2026, CAISO released a 2026 white paper on transmission capability estimates for the CPUC’s resource planning, replacing the 2024 version. The paper explains that these estimates are a key input to the CPUC’s resource model and its mapping of resources to substations, that CAISO uses the CPUC’s portfolios in its annual Transmission Planning Process, and that the same numbers are used in generation interconnection screening. On July 30, CAISO posted revisions adding nine PG&E Greater Bay Area constraints and updating SCE Northern Area constraint information.
The link to interconnection is direct for energy-only requests. CAISO’s zonal intake limits for Cluster 16 energy-only interconnection requests are based on the CPUC base case portfolio, using the 2036 mapped portfolio from the CPUC’s September 30, 2025 ruling. The table sets a 150 percent intake limit of 3,825 megawatts in the PG&E Fresno Study Area, against 2,550 megawatts in the portfolio, and 4,635 megawatts in the PG&E Kern Study Area, against 3,090 megawatts. CAISO said the Cluster 16 interconnection request window would open October 1, 2026, and it posted a Cluster 16 queue report on October 16.
Who is affected
- Load-serving entities. Utilities, community choice aggregators, and electric service providers carry the filing obligation and the procurement obligations under Decision 26-02-057.
- Solar, storage, geothermal, and wind developers. Each plan’s action plan describes the LSE’s procurement activities, and the procurement decision requires at least one-quarter of the procurement due by 2032 to come from clean firm or long-duration storage resources.
- Landowners and counties in study areas with planned capacity. The Fresno and Kern figures set the energy-only intake limits for Cluster 16 in those zones.
- Nearby communities. Each plan must address disadvantaged communities and local air emissions.
- Large-load customers. The assigned load forecasts address data center load directly: the January ruling describes a separate peak calculation for data center sales using a CEC peak-to-energy ratio for data centers.
The plans, comments, and later Commission decisions build one public record, and the comment period on the individual plans, which closed September 21, 2026, was a chance to add local facts about land, transmission, and community impacts. Later rulings and proposed decisions in the proceeding are the next points to add to that record. Agencies, counties, and project sponsors can see how DBMAC approaches agency proceedings and hearings on its government relations page.
What to watch
- September 21, 2026 (passed): Deadline for any party to file initial comments on any or all individual plans.
- October 1, 2026 (passed): The Cluster 16 interconnection request window was scheduled to open, with energy-only intake limits tied to the CPUC base case portfolio.
- Aggregation and the next portfolios: After aggregating the filings, the Commission moves toward adopting the next Preferred System Plan and recommending portfolios for transmission planning, according to the January 16 ruling.
- June 1, 2030: The first 2,000 megawatts of procurement under Decision 26-02-057 must be online and delivering to the grid.
CAISO describes its transmission capability figures as just estimates, and the final determination of needed upgrades is made in the policy-driven assessment within its Transmission Planning Process. Anyone tracking a specific site should follow both the R.25-06-019 docket and CAISO’s transmission planning notices.