High-Speed Rail

High-Speed Rail Heavy Maintenance Facility: The Fresno and Hanford Sites

The Authority's scoping period for its Central Valley Heavy Maintenance Facility closed on September 14, 2026, with one candidate site in Fresno County and one near Hanford. A separate filing exempts a six-story operations control center south of Fresno from further CEQA review.

Daron McDaniel

By Principal, DBMAC Strategies

Published Last updated 8 min read

The California High-Speed Rail Authority’s search for a high-speed rail heavy maintenance facility in the Central Valley reached a public milestone on September 14, 2026. The scoping period for the proposed Central Valley Heavy Maintenance Facility (HMF), when agencies, landowners, and residents could tell the Authority what its environmental review should cover, ran from August 14 through September 14, 2026. Scoping closed September 14, 2026, and comment letters from state agencies are posted on CEQAnet. Two candidate sites remain: one in Fresno County and one in Kings County near Hanford, according to the Authority’s announcement.

A second filing in the same corridor landed in early September. On September 3, the State Clearinghouse received the Authority’s Notice of Exemption for a six-story Operations Control Center building at the Operation and Maintenance Facility planned south of Fresno, relying on a CEQA exemption the Legislature created in 2025 for high-speed rail maintenance facilities. Together, the two filings show where the system’s long-term operations workforce is being located, and which local governments, landowners, and suppliers sit closest to it.

What happened

The Authority filed a Notice of Preparation of a Draft Environmental Impact Report for the HMF with the State Clearinghouse on August 14, 2026, under State Clearinghouse number 2026080484. The notice describes a facility that would support the full range of Phase 1 operation and maintenance activities, from San Francisco to Los Angeles and Anaheim, including crewing, servicing, heavy repairs, and storage of trains, along with space for staff and operations management.

The Authority’s announcement, republished by the Sierra Sun Times on August 15, describes the HMF as the primary location for inspections, servicing, maintenance, overhaul, and major component replacement for the high-speed train fleet. It scheduled three scoping meetings, each from 5 to 6 p.m.: in Fresno on August 25, in Hanford on August 26, and on Zoom on August 27. Comments could be sent by email to HMF@hsr.ca.gov with the subject line “Central Valley HMF Scoping Comment,” by phone, or by mail to the Authority’s Director of Environmental Services in Sacramento.

Separately, an Authority memorandum dated August 31, 2026 concluded that the Operations Control Center (OCC) building qualifies for a statutory CEQA exemption and that no additional CEQA documentation is required. The Notice of Exemption was received and posted on September 3.

Key details and timeline

The two HMF sites

The State Clearinghouse record lists the Fresno County site near East Malaga Avenue and South Cedar Avenue and the Kings County site near State Route 43 and Iona Avenue in Hanford, with total acreage shown as 200 to 400 acres. Present land use for the Fresno County site is listed as limited agriculture, exclusive agriculture, and heavy industrial; for the Kings County site, agriculture, public, very low density residential, and general agriculture. The record also lists BNSF and Union Pacific rail lines, State Routes 99, 41, and 198, and Hanford Municipal Airport among nearby features.

The two sites came out of a screening process that began in late 2023, in which the Authority refined an initial list of 11 potential sites down to two. The Fresno Bee reported the screening criteria as operation needs, land use compatibility, construction feasibility, community impacts and environmental considerations.

What the facility would include

According to the Notice of Preparation, both HMF alternatives include:

  • Two independent points of access to the high-speed rail mainline, stabling tracks for trainsets not in service, and servicing platforms for cleaning and preparing trains.
  • Vehicle maintenance shops for light and heavy maintenance, low-speed dynamic and static testing, and a wheel reprofiling track.
  • A component shop campus to support long-term operational resilience of the Phase 1 system and domestic supply-chain security for critical parts, components, and specialist services.
  • A solar array and battery energy storage system to support HMF operations.
  • Parking, access roads (including improvements to the adjacent roadway network), stormwater detention ponds, utilities, fencing, and support buildings that could include a substation and an emergency generator.

Timeline

  • Late 2023: Site screening begins, per the Authority.
  • August 14, 2026: Notice of Preparation received by the State Clearinghouse; scoping opens.
  • August 25 to 27, 2026: Scoping meetings in Fresno, Hanford, and online.
  • August 31, 2026: OCC exemption memorandum issued to the Authority’s Director of Environmental Services.
  • September 3, 2026: OCC Notice of Exemption received and posted.
  • September 14, 2026: HMF scoping period closes.
  • Early 2027: The Authority expects to release the Draft Environmental Impact Report/Environmental Impact Statement, with the final document going to its Board of Directors for approval in mid to late 2027.

The Operations Control Center and the SB 131 exemption

The OCC belongs to a different facility than the HMF. It is part of the Operation and Maintenance Facility planned south of the City of Fresno, which the Authority’s exemption notice says will support day-one operations and long-term maintenance of the system. The notice lists the location near East American Avenue and South Cedar Avenue. The Authority’s memorandum states that the building would accommodate up to 200 staff for maintenance, operations, engineering, technical support, and administrative activities.

The exemption comes from Senate Bill 131, which the memorandum states the Legislature adopted on June 30, 2025, adding Section 21080.70 to the Public Resources Code. As reproduced in the memorandum, the section exempts a heavy maintenance facility or other maintenance facility for electrically powered high-speed rail when the project was evaluated in a prior project-level EIR that looked at similar maintenance facility sites, incorporates the applicable mitigation measures from those reports, and sits within one mile of right-of-way approved for high-speed rail service. It does not apply on natural and protected lands as defined in the code, and a parallel provision covers high-speed rail passenger stations within the study area of a previously certified EIR.

For the OCC, the memorandum relies on the 2014 Fresno to Bakersfield Final EIR/EIS and a 2020 reexamination. It also states that the Authority has already obtained the OMF property, including the OCC site, through right-of-way acquisitions for its civil construction packages.

Who is affected

  • Landowners and agricultural operators at and near the two HMF sites. The State Clearinghouse record lists the assessor’s parcel numbers for both the Fresno County and Kings County alternatives, along with the agricultural and industrial land use designations described above.
  • Fresno County, Kings County, and the Cities of Fresno and Hanford. The project includes access roads, improvements to the adjacent roadway network, stormwater ponds, and utilities, all of which touch local infrastructure and planning.
  • Schools and nearby residents. The record lists Malaga Elementary, Orange Center Elementary, and Washington Colony Elementary near the Fresno County site.
  • Workers and workforce programs. The Authority anticipates total long-term employment at the site, including associated facilities, of approximately 1,700 to 2,100 positions at full buildout of Phase 1.
  • Suppliers and contractors. The component shop campus is framed around domestic supply-chain security. The Authority’s 2026 Business Plan, released June 1, 2026, lists soliciting bids for the operations control center and identifying contractors for a maintenance facility bid among the procurement milestones it expects in the fourth quarter of 2026. As of October 26, 2026, the Authority’s procurement schedule lists the Maintenance Facility/Operations Control Center procurement as upcoming, with the solicitation date and award still to be determined.

For a city, county, or landowner near either candidate site, the practical questions are the ones the environmental review will work through: road access, utility capacity, land use compatibility, and where a workforce of that size would come from. Those are the same questions DBMAC works through with employers and public agencies in its economic development and site analysis work.

What to watch

  • Scoping comments. Scoping closed September 14, 2026, and comment letters from the California Department of Fish and Wildlife, the Department of Conservation, and the Native American Heritage Commission are posted on CEQAnet. According to the Authority, input received during scoping helps inform the environmental review and the preparation of the Draft EIR/EIS.
  • Draft EIR/EIS (early 2027). The draft is the next opportunity for public comment. The Notice of Preparation states the EIR will examine a range of HMF alternative sites and a No Project Alternative, with project-level analysis of construction, operation, and maintenance impacts and site-specific mitigation. The Authority has said it expects the draft in early 2027.
  • Procurement. The fourth-quarter 2026 milestones in the final 2026 Business Plan are the points at which contractors and suppliers can see what the Authority intends to bid for the operations control center and maintenance facilities. The Authority’s procurement schedule is the place to watch for the solicitation date, which it currently lists as to be determined.
  • Use of the SB 131 exemption. The OCC filing is an example of how the Authority is applying Section 21080.70 at a site already studied in the Fresno to Bakersfield environmental record. The HMF, by contrast, is going through a new EIR.

The State Clearinghouse records for the HMF and the OCC are the places to follow later filings on both facilities.

Frequently asked questions

Where are the candidate sites for the high-speed rail heavy maintenance facility?

Two sites remain. The State Clearinghouse record lists one in Fresno County near East Malaga Avenue and South Cedar Avenue and one near State Route 43 and Iona Avenue in Hanford, Kings County, with total acreage shown as 200 to 400 acres. The Authority narrowed an initial list of 11 potential sites to these two.

How could the public comment during scoping on the Central Valley HMF?

The Authority's announcement listed three options: email HMF@hsr.ca.gov with the subject line "Central Valley HMF Scoping Comment," call the project line, or mail comments to the Director of Environmental Services in Sacramento. The scoping period ran from Aug. 14 to Sept. 14; the next comment opportunity is the Draft EIR/EIS, which the Authority expects in early 2027.

How many jobs would the heavy maintenance facility support?

The Authority anticipates that total long-term employment at the site, including associated facilities, would range from approximately 1,700 to 2,100 positions at full buildout of the Phase 1 system between San Francisco and Los Angeles/Anaheim.

What is the SB 131 exemption for high-speed rail maintenance facilities?

SB 131 (Chapter 24, Statutes of 2025), enacted June 30, 2025, added Public Resources Code Section 21080.70. As reproduced in an Authority memorandum, it exempts high-speed rail maintenance facilities from CEQA when a prior project-level EIR evaluated similar sites, applicable mitigation is incorporated, and the site is within one mile of approved high-speed rail right-of-way, excluding natural and protected lands.

Sources

  1. California High-Speed Rail Central Valley Heavy Maintenance Facility Project (SCH No. 2026080484), Notice of Preparation (opens in a new tab)Governor's Office of Land Use and Climate Innovation, CEQAnet (lead agency: California High-Speed Rail Authority), Received August 14, 2026
  2. High-Speed Rail Operations Control Center (OCC) Building (SCH No. 2026090189), Notice of Exemption (opens in a new tab)Governor's Office of Land Use and Climate Innovation, CEQAnet (lead agency: California High-Speed Rail Authority), Received September 3, 2026
  3. CEQA Statutory Exemption under PRC §21080.70 (SB 131) for the High-Speed Rail Operations Control Center Building (memorandum) (opens in a new tab)California High-Speed Rail Authority, August 31, 2026
  4. 2026 Business Plan (final plan, released June 1, 2026) (opens in a new tab)California High-Speed Rail Authority, June 1, 2026
  5. California High-Speed Rail Seeks Public Input on Proposed Central Valley Heavy Maintenance Facility Site (opens in a new tab)Sierra Sun Times (California High-Speed Rail Authority announcement), August 15, 2026
  6. High-speed rail seeks public input on proposed Fresno, Hanford maintenance sites (opens in a new tab)The Fresno Bee (via Yahoo News), August 25, 2026
  7. Procurement Schedule (opens in a new tab)California High-Speed Rail Authority, Checked October 26, 2026

Economic development

Near a high-speed rail maintenance site? Plan around it early.

A facility of this size brings road, utility, land use, and workforce questions to the jurisdictions and landowners around it. DBMAC Strategies helps Central Valley agencies, landowners, and employers assess sites, map the local approvals involved, and position for the economic activity that follows major public facilities.