High-Speed Rail

High-Speed Rail Right-of-Way Acquisition: What Landowners and Businesses Between Merced and Bakersfield Should Know

The Authority estimates 500 more parcels are needed for the Merced and Bakersfield extensions. Here is how appraisals, offers, State Public Works Board hearings, and relocation benefits work for owners and tenants near the alignment.

Daron McDaniel

By Principal, DBMAC Strategies

Published Last updated 9 min read

High-speed rail right-of-way acquisition is moving from the 119-mile Central Valley construction zone to the extensions at each end of the Merced to Bakersfield segment. The California High-Speed Rail Authority’s final 2026 Business Plan, released June 1, 2026, cites an estimated 500 additional parcels for the Merced and Bakersfield extensions, and the State Public Works Board has adopted resolutions authorizing eminent domain for Authority parcels in Kern, Madera, and Fresno counties and in Kings County this year.

For a landowner, farm operator, or business owner near the alignment, the process follows a defined sequence set by state and federal law. This guide, written at the end of June 2026 and updated in October 2026, walks through that sequence: where right-of-way work stands, how appraisals and offers work, what the State Public Works Board decides, and which relocation benefits apply.

Where right-of-way stands on the Merced to Bakersfield segment

The Authority describes the project as a 171-mile program from Merced to Bakersfield. On the 119-mile Central Valley segment already under construction, the final 2026 Business Plan reports that all 2,288 parcels (100 percent) had been delivered to the design-build teams as of February 2026. The project schedules in the same plan list right-of-way as in progress for both the Merced Extension and the Bakersfield Extension, and the plan gives 2032 as the updated completion date for the Merced to Bakersfield early operating segment.

The plan also describes how the Authority handles parcels that do not settle. Where landowner offers remain unaccepted and no settlement is reached, the Authority initiates condemnation to prevent early works and construction delays, and it is coordinating with the Judicial Council to secure designated judges for right-of-way cases. The Authority released the draft plan for public comment on February 28, 2026; the comment period closed April 29, 2026, and the Authority released the final plan on June 1, 2026.

How the acquisition process works

California’s property acquisition statutes, reproduced in Caltrans’ Right of Way Manual, Chapter 8, set out the core steps a public entity follows. The State Public Works Board’s records show the same steps in the Authority’s recent cases.

  1. Appraisal and inspection. Under Government Code Section 7267.1, property is appraised before negotiations begin, and the owner or a designated representative is given an opportunity to accompany the appraiser during the inspection.
  2. First written offer. Under Section 7267.2, the agency sets an amount it believes is just compensation and offers the full amount, which can be no less than its approved appraisal of fair market value. The owner receives a written statement and summary of the basis for that amount, with compensation for the property and damages to the remaining property stated separately where appropriate.
  3. Independent appraisal. Code of Civil Procedure Section 1263.025 requires the agency to offer to pay the reasonable costs, not to exceed $5,000, of an independent appraisal ordered by the owner from a licensed appraiser.
  4. Negotiation. Section 7267.1 directs the agency to make every reasonable effort to expeditiously acquire real property by negotiation, and Section 7267.5 bars coercive actions intended to compel agreement on price.
  5. Notice of intent and resolution of necessity. If no agreement is reached, State Public Works Board staff mail the owner a notice of intent to adopt a resolution of necessity, in accordance with Code of Civil Procedure Section 1245.235. Caltrans’ manual, citing the same section, states that owners must file a written request to appear within 15 days of the mailing of the notice.
  6. Condemnation. An adopted resolution gives the agency the right to file a condemnation action and, with the approval of the Superior Court, take possession of the property.

Two other provisions matter for partial takes and timing. If a partial acquisition would leave an uneconomic remnant, the agency shall offer to acquire the entire property if the owner wants it to. And to the greatest extent practicable, no one lawfully occupying the property is required to move without at least 90 days’ written notice.

What the State Public Works Board decides, and what it does not

Under California Eminent Domain Law, the State Public Works Board acts as the governing body of the Authority for adopting resolutions of necessity. To adopt one, the Board must consider four conditions: the public interest and necessity require the project; the project is located for the greatest public good and least private injury; the property is necessary for the project; and the Section 7267.2 offer has been made to the owners of record.

The Board’s 2026 meetings on Authority properties show how this works in practice (list updated October 27, 2026):

  • January 12, 2026. The Board took up twelve resolutions of necessity for Authority properties: ten in Kern County, one in Madera County, and one in Fresno County. First written offers had gone out between April and October 2025. Representatives of seven properties submitted objections, the Board heard the opposed and unopposed items separately, and it approved all twelve.
  • February 6, 2026. The Board adopted four resolutions for properties in Kern and Fresno counties. According to the staff analysis, first written offers were made between August and November 2025, and the notices of intent were mailed January 21, 2026.
  • March 18, 2026. The Board adopted two resolutions of necessity for properties in Madera County. First written offers had gone out in December 2025, and the notices of intent were mailed February 19, 2026. The Board adopted the unopposed resolution 3-0, then heard the owner’s objection to the other separately and adopted it 3-0. An item for two Kern County properties was pulled from the April 22 agenda.
  • May 20, 2026. The Board took up five resolutions of necessity: two in Kings County, one in Madera County, and two in Kern County. First written offers had gone out between September 2025 and January 2026. The Board adopted the four unopposed resolutions 3-0, then heard the owner’s objection to one Kern County property separately and adopted that resolution 3-0.
  • July 30, 2026. The Board adopted three resolutions of necessity, one each in Fresno, Kern, and Madera counties, 3-0. First written offers had gone out between February and April 2026, and the notices of intent were mailed June 24, 2026.
  • August 19, 2026. The Board adopted one resolution of necessity for a Fresno County property, 3-0. The first written offer went out in March 2026, and the notice of intent was mailed July 16, 2026.
  • September 16, 2026. Five properties or interests were on the agenda: two in Kern County, two in Fresno County, and one in Kings County. One Fresno County owner settled before the meeting, so that item was not presented. The Board adopted the three unopposed resolutions 3-0, then heard the owner’s objection to the other Fresno County property separately and adopted that resolution 3-0. First written offers had gone out between March and May 2026.

The scope of the Board’s review is narrow. At the February meeting, Board counsel stated that concerns about compensation or property value were not considered by the State Public Works Board in deciding whether to adopt a resolution, and that adoption did not preclude continued negotiations. At the January meeting, counsel confirmed that a resolution of necessity addresses the necessity of the parcel, not the value. For an owner, that means the Board hearing is not the venue for a valuation dispute; value remains a matter for negotiation after the vote.

Relocation benefits for businesses, farms, and residents

Payment for the property and relocation assistance are separate. The Authority’s relocation brochure for displaced businesses, farms, and nonprofits states that a payment for loss of goodwill is considered an acquisition cost and that relocation payments cannot duplicate it. The brochure is built on the federal Uniform Relocation Assistance and Real Property Acquisition Policies Act, and it states that relocation payments are not available until the first written offer has been made.

The federal regulations that implement the Uniform Act were amended by a rule that took effect June 3, 2024. Under the amended rule:

  • A small business, farm, or nonprofit may receive up to $33,200 for reestablishment expenses at a replacement site, in addition to moving costs.
  • A displaced business that meets the eligibility tests may instead choose a fixed payment equal to its average annual net earnings, but not less than $1,000 nor more than $53,200.
  • A replacement housing payment for an eligible 90-day homeowner-occupant may not exceed $41,200, and rental assistance for an eligible displaced tenant may not exceed $9,570.

The business brochure text is dated June 23, 2011, and the fixed-payment range it lists predates the 2024 rule, so owners should confirm current amounts with the relocation agent assigned to them.

Who is affected

What landowners and businesses can do now

The record from recent cases points to practical steps an owner can take before an offer arrives:

  • Assemble records that support value and operations: leases, rent rolls, crop and irrigation records, and equipment lists. The fixed payment is based on average annual net earnings for the two taxable years immediately preceding the displacement, so those returns matter.
  • Attend the appraiser’s inspection, and use the independent appraisal reimbursement once an offer arrives.
  • Watch for mailings from the State Public Works Board; the window to request to appear is short.
  • For an operating business, start the replacement-site search early, since a new location has its own power, water, zoning, and permit requirements. DBMAC’s economic development practice works with owners on site selection and the local approvals a relocation needs.
  • For help preparing for a resolution of necessity hearing and organizing the conversation with agency staff, alongside your own attorney and appraiser, see DBMAC’s page for landowners.

The timing for any given parcel depends on where it sits in the Authority’s acquisition plan. Owners can follow the State Public Works Board’s meeting agendas and the Authority’s Business Plan updates for the extensions to see when the next resolutions are scheduled.

Frequently asked questions

Who approves eminent domain for California high-speed rail property?

The State Public Works Board. Under California Eminent Domain Law it serves as the governing body of the High-Speed Rail Authority for adopting resolutions of necessity. It must consider whether the project is required, located for the greatest public good and least private injury, whether the property is necessary, and whether the required offer was made.

Can I keep negotiating after a resolution of necessity is adopted?

Yes. At the Board's February 6, 2026 meeting, its counsel stated that adopting the resolutions did not preclude continued negotiations toward a mutually agreeable acquisition. Counsel also stated that concerns about compensation or property value were not considered in deciding whether to adopt a resolution.

Will the Authority pay for my own appraisal?

State law requires a public entity making an offer under threat of eminent domain to offer to pay the reasonable costs, not to exceed $5,000, of an independent appraisal ordered by the owner. The appraiser must be licensed by the state's real estate appraiser licensing office.

What relocation payments can a displaced business receive?

Under the federal Uniform Act rule effective June 3, 2024, a small business, farm, or nonprofit may receive up to $33,200 in reestablishment expenses plus moving costs, or an eligible business may choose a fixed payment of $1,000 to $53,200 based on average annual net earnings.

How much notice do I get before I have to move?

Government Code Section 7267.3 provides that, to the greatest extent practicable, no one lawfully occupying the property is required to move a home, business, or farm without at least 90 days' written notice of the date by which the move is required.

Sources

  1. 2026 Business Plan (final plan, released June 1, 2026) (opens in a new tab)California High-Speed Rail Authority, June 1, 2026
  2. Staff Analysis, February 6, 2026 Meeting (Action Item 1: High-Speed Rail Authority, Merced to Bakersfield Segment) (opens in a new tab)State Public Works Board, February 6, 2026
  3. Final Minutes, February 6, 2026 (opens in a new tab)State Public Works Board, February 6, 2026
  4. Final Minutes, January 12, 2026 (opens in a new tab)State Public Works Board, January 12, 2026
  5. Right of Way Manual, Chapter 8: Acquisition (opens in a new tab)California Department of Transportation, Revised July 2025
  6. Palmdale to Burbank Project Section Final EIR/EIS, Appendix 3.12-A: Residential, Business, and Mobile Home Relocation and Assistance Brochures (opens in a new tab)California High-Speed Rail Authority, April 2024
  7. Uniform Relocation Assistance and Real Property Acquisition for Federal and Federally Assisted Programs (Final Rule, 89 FR 36908) (opens in a new tab)Federal Highway Administration, Federal Register, May 3, 2024
  8. Final Minutes, May 20, 2026 (opens in a new tab)State Public Works Board, May 20, 2026
  9. 2026 Business Plan (Authority web page) (opens in a new tab)California High-Speed Rail Authority, Accessed October 27, 2026
  10. Final Minutes, March 18, 2026 (opens in a new tab)State Public Works Board, March 18, 2026
  11. Final Minutes, July 30, 2026 (opens in a new tab)State Public Works Board, July 30, 2026
  12. Final Minutes, August 19, 2026 (opens in a new tab)State Public Works Board, August 19, 2026
  13. Final Minutes, September 16, 2026 (opens in a new tab)State Public Works Board, September 16, 2026

Economic development

Property near the high-speed rail alignment? Plan the next site early.

When an operating business or farm has to move, the replacement site needs its own power, water, zoning, and local approvals. DBMAC Strategies helps owners in the Merced to Bakersfield corridor evaluate replacement sites and map the approvals a relocation requires, working alongside the owner's own legal counsel and appraiser.

Any matter before a public body on which Daron holds or has held a seat, whether county, regional, or statewide, is reviewed for conflicts before any substantive conversation. See all of his seats.